Overview
Both are HAMAC machines, but they solve different problems. This compares the PE Series Jaw Crusher and PF Impact Crusher so you can specify the right stage.

Breakage mechanism
- PE Series Jaw Crusher: Jaw crushers are often used for primary crushing in mine material crushing.
- PF Impact Crusher: The impact crusher (impact crusher) is a new generation of impact crusher develo
Best use
- PE Series Jaw Crusher: primary reduction / robust duty.
- PF Impact Crusher: The impact crusher (impact crusher) is a new generation of impact crusher develo.
Decision checklist
- Hard abrasive rock → compression (cone/jaw).
- Soft rock + shape → impact.
- Sand / shape → VSI.
- Moving site → mobile.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | PE Series Jaw Crusher |
| Category | Jaw Crusher |
| Assumed duty | continuous quarry production |
| Evaluation horizon | seven-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Published PE Series Jaw Crusher model data
| Model | Input Size | Max Feeding Size | Output Range | Capacity | Engine Power | Weight |
|---|---|---|---|---|---|---|
| PEX250x750 | 250x750 mm | 210 mm | 25-60 mm | 13-35 T/H | 30 KW | 5.5 T |
| PEX250x1000 | 250x1000 mm | 210 mm | 25-60 mm | 16-52 T/H | 37 KW | 7 T |
| PEX250x1200 | 250x1200 mm | 210 mm | 25-60 mm | 20-61 T/H | 55 KW | 9.5 T |
| PEX300x1300 | 300x1300 mm | 250 mm | 20-90 mm | 16-105 T/H | 75 KW | 15.6 T |
| PE400×600 | 400×600 mm | 340 mm | 40-100 mm | 16-60 T/H | 30 KW | 6.7 T |
| PE500×750 | 500×750 mm | 425 mm | 50-100 mm | 40-110 T/H | 55 KW | 11.7 T |
| PE600×900 | 600×900 mm | 500 mm | 65-180 mm | 80-180 T/H | 55-75 KW | 16.1 T |
| PE750×1060 | 750×1060 mm | 630 mm | 80-180 mm | 110-320 T/H | 90-110 KW | 30.1 T |
Jaw crushers are often used for primary crushing in mine material crushing. Read the table column by column against continuous quarry production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | seven-year view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for pe series jaw crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
A HAMAC project manager stays with the order from the first data sheet through hand-over in your market.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for your market.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Whether the quoted t/h is achieved at continuous quarry production or under ideal laboratory feed.
- Closed-side setting range and whether automatic setting regulation is included.
- Product sampling points and the lab equipment needed for routine grading checks.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Energy draw in kW and the expected kWh per tonne at the design duty.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Using one liner profile for both secondary and tertiary stages.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Overlooking dust, noise and water permits in your market until erection has already started.
For continuous quarry production, protect the lowest cost per tonne requirement explicitly in the contract documents.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm the direction and tension of every belt under no load.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
- Confirm all guards, emergency stops and pull-wire switches function.
- Record the baseline grading curve for each product fraction.
On a greenfield site, allow extra time for the dust and noise measurements.