Overview
HAMAC equipment matched to metal ore & mining:

Equipment
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- Symons Cone Crusher
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Application | Metal Ore & Mining |
| Typical feed | Iron ore, Copper ore, Gold ore, Manganese ore |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | seven-year view |
Treat this as a living sheet. Every revision of the flow sheet for your market should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
On manufactured-sand production, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.
What to verify before you sign
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Local service partner, technician travel time and visa requirements for your market.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Control system language, telemetry and remote diagnostics availability.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a confined urban yard.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying maximum mechanical availability on price alone and losing it in availability.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Verify rotation direction on every motor before coupling.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Check belt tracking, chute build-up and transfer-point dust.
On a confined urban yard, allow extra time for the dust and noise measurements.
