Design basis for limestone remote site
The design basis starts with the rock, not the machine. Limestone is rated at 30–150 MPa compressive strength with low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.35 t/m³. Soft and non-abrasive enough for impact crushing in a single stage; clay seams and moisture are the usual complications. The reference conditions should be attached to every figure quoted.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of 0–5, 5–20, 20–40 mm and ground filler.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Limestone · 30–150 MPa · abrasion low |
| Design throughput | 110 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | 0–5, 5–20, 20–40 mm and ground filler |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | jaw or impact → screen → optional grinding mill |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a limestone remote site this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For limestone at 110 t/h the working train is jaw or impact → screen → optional grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for limestone and for a softer rock. The reference conditions should be attached to every figure quoted.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 300 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 70% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–20, 20–40 mm and ground filler |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 300 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for limestone, while energy and spares autonomy determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
The reference conditions should be attached to every figure quoted. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.