Design basis for iron ore underground mine
The design basis starts with the rock, not the machine. Iron ore is rated at 80–250 MPa compressive strength with medium–high abrasiveness, medium moisture sensitivity and a loose bulk density around 2.10 t/m³. High bulk density means belts and bins must be sized by mass, while moisture drives screen blinding in the fines circuit. A change in one stage changes the circulating load in all the others.
A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of −10 mm fines and sized lump ore.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Iron ore · 80–250 MPa · abrasion medium–high |
| Design throughput | 110 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | −10 mm fines and sized lump ore |
| Loose bulk density | 2.10 t/m³ |
| Suggested circuit | jaw / gyratory → cone → screen → magnetic separation |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a iron ore underground mine this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For iron ore at 110 t/h the working train is jaw / gyratory → cone → screen → magnetic separation. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for iron ore and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 2.10 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 240 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 30% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm fines and sized lump ore |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 240 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for iron ore, while compact footprint determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.