Design basis for calcite greenfield plant
The design basis starts with the rock, not the machine. Calcite is rated at 30–90 MPa compressive strength with very low abrasiveness, low moisture sensitivity and a loose bulk density around 1.35 t/m³. Whiteness and D97 control drive the circuit; contamination control and classifier stability are the priority. A change in one stage changes the circulating load in all the others.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 250 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of 200–2500 mesh GCC filler.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Calcite · 30–90 MPa · abrasion very low |
| Design throughput | 250 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | 200–2500 mesh GCC filler |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | jaw → impact → Raymond / ball mill + classifier |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a calcite greenfield plant this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For calcite at 250 t/h the working train is jaw → impact → Raymond / ball mill + classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for calcite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~313 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 610 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 70% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 250 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 200–2500 mesh GCC filler |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 610 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for calcite, while a verifiable mass balance determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 250 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
