Design basis for limestone remote site
The design basis starts with the rock, not the machine. Limestone is rated at 30–150 MPa compressive strength with low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.35 t/m³. Soft and non-abrasive enough for impact crushing in a single stage; clay seams and moisture are the usual complications. Record the setting before adjusting it, or the baseline is lost.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 90 t/h of saleable product, with a maximum feed top size near 350 mm and target fractions of 0–5, 5–20, 20–40 mm and ground filler.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Limestone · 30–150 MPa · abrasion low |
| Design throughput | 90 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~350 mm |
| Target product | 0–5, 5–20, 20–40 mm and ground filler |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | jaw or impact → screen → optional grinding mill |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a limestone remote site this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For limestone at 90 t/h the working train is jaw or impact → screen → optional grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for limestone and for a softer rock. Record the setting before adjusting it, or the baseline is lost.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~113 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 50% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 240 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 50% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 90 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–20, 20–40 mm and ground filler |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 240 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for limestone, while energy and spares autonomy determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 50% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 90 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Record the setting before adjusting it, or the baseline is lost. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
