Design basis for gold ore wet tropical climate
The design basis starts with the rock, not the machine. Gold ore is rated at 60–200 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.80 t/m³. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. Measurements are only comparable when the sieve standard is the same.
A wet tropical climate must keep screening reliable through a long rainy season, constrained by high feed moisture and clay-bearing overburden. The commercial priority is wet screening and washing. For this combination HAMAC works from an indicative design point of 140 t/h of saleable product, with a maximum feed top size near 500 mm and target fractions of −10 mm mill feed or heap-leach agglomerate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gold ore · 60–200 MPa · abrasion medium |
| Design throughput | 140 t/h saleable product (120–300 t/h scenario band) |
| Maximum feed size | ~500 mm |
| Target product | −10 mm mill feed or heap-leach agglomerate |
| Loose bulk density | 1.80 t/m³ |
| Suggested circuit | jaw → cone / impact → screen |

Why excessive liner consumption appears in this circuit
Liner sets are replaced far more often than the budget assumed. In a gold ore wet tropical climate this is usually a system symptom rather than a single machine fault. A supplier can only guarantee a figure when the test conditions are written down.
- the alloy does not match feed abrasiveness
- the crusher is running with a worn chamber profile
- tramp metal is reaching the chamber
Indicative values are starting points for a design, not guarantees. Before changing a crusher setting, check these in order: 1) weigh each liner set before and after use; 2) calculate cost per saleable tonne; 3) photograph the chamber at every change-out. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For gold ore at 140 t/h the working train is jaw → cone / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gold ore and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~175 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone / impact |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.80 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 450 kW order-of-magnitude connected load |
The corrective actions for excessive liner consumption are applied on top of this base circuit: select manganese grade against measured silica content; rotate or replace liners before the profile is lost; install a magnet and metal detector on the feed belt.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 40% and a screen efficiency target above 90%. Indicative values are starting points for a design, not guarantees.
- Weigh each liner set before and after use
- Calculate cost per saleable tonne
- Photograph the chamber at every change-out
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 140 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm mill feed or heap-leach agglomerate |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 450 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gold ore, while wet screening and washing determines how much lost production actually costs. A supplier can only guarantee a figure when the test conditions are written down.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 140 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.