Design basis for andesite underground mine
The design basis starts with the rock, not the machine. Andesite is rated at 120–240 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.44 t/m³. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. A change in one stage changes the circulating load in all the others.
A underground mine must fit crushing equipment into a confined excavation, constrained by restricted headroom, ventilation and haulage access. The commercial priority is compact footprint. For this combination HAMAC works from an indicative design point of 140 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of asphalt aggregate, 0–5, 5–16 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Andesite · 120–240 MPa · abrasion medium–high |
| Design throughput | 140 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | asphalt aggregate, 0–5, 5–16 mm |
| Loose bulk density | 1.44 t/m³ |
| Suggested circuit | jaw → cone → VSI → screen |

Why unplanned downtime appears in this circuit
Short stops accumulate into a large annual output loss. In a andesite underground mine this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- no planned change-out window for wear parts
- spares with long lead times are not held on site
- interlock and lubrication faults are cleared without root-cause logging
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) report availability and utilisation separately each month; 2) review the top five stop causes; 3) verify spares stock against the recommended list. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For andesite at 140 t/h the working train is jaw → cone → VSI → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for andesite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~175 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 60% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.44 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 340 kW order-of-magnitude connected load |
The corrective actions for unplanned downtime are applied on top of this base circuit: schedule liner changes by measured wear rate, not by calendar; hold a recommended spares list for the first two years; log every stop with a fault code and a corrective action.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 60% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Report availability and utilisation separately each month
- Review the top five stop causes
- Verify spares stock against the recommended list
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 140 t/h nominal |
| Grading | Full sieve analysis, agreed standard, asphalt aggregate, 0–5, 5–16 mm |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 340 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for andesite, while compact footprint determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 60% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 140 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.