Design basis for gold ore greenfield plant
The design basis starts with the rock, not the machine. Gold ore is rated at 60–200 MPa compressive strength with medium abrasiveness, medium moisture sensitivity and a loose bulk density around 1.80 t/m³. Quartz veins create variable hardness across the face; the plant must tolerate feed changes without re-setting every stage. A change in one stage changes the circulating load in all the others.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 200 t/h of saleable product, with a maximum feed top size near 400 mm and target fractions of −10 mm mill feed or heap-leach agglomerate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gold ore · 60–200 MPa · abrasion medium |
| Design throughput | 200 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~400 mm |
| Target product | −10 mm mill feed or heap-leach agglomerate |
| Loose bulk density | 1.80 t/m³ |
| Suggested circuit | jaw → cone / impact → screen |

Why variable feed gradation appears in this circuit
Crusher power draw swings sharply with each loader cycle. In a gold ore greenfield plant this is usually a system symptom rather than a single machine fault. Two plants with the same nominal t/h can have very different operating costs.
- segregation in the stockpile and the dump hopper
- no surge buffer between the loader and the primary feeder
- hard and soft bands are exposed simultaneously at the face
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) sample feed gradation at three points across the belt; 2) record power draw at one-minute intervals; 3) check hopper level alarms and feeder response. HAMAC states nominal values alongside the conditions they were measured under.
Recommended equipment configuration
For gold ore at 200 t/h the working train is jaw → cone / impact → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gold ore and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~250 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~38 mm at the secondary stage |
| Secondary / tertiary | cone / impact |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.80 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 540 kW order-of-magnitude connected load |
The corrective actions for variable feed gradation are applied on top of this base circuit: blend feed from two stockpile faces; add a hopper with level control and a vfd feeder; set the drive power margin for the hardest band, not the average.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 38 mm, a circulating load around 20% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Sample feed gradation at three points across the belt
- Record power draw at one-minute intervals
- Check hopper level alarms and feeder response
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 200 t/h nominal |
| Grading | Full sieve analysis, agreed standard, −10 mm mill feed or heap-leach agglomerate |
| Crusher setting | CSS measured and logged, ~38 mm starting point |
| Power | Main-drive current at steady feed, 540 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
HAMAC states nominal values alongside the conditions they were measured under. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gold ore, while a verifiable mass balance determines how much lost production actually costs. Two plants with the same nominal t/h can have very different operating costs.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 200 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. HAMAC states nominal values alongside the conditions they were measured under. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.