Design basis for construction & demolition waste greenfield plant
The design basis starts with the rock, not the machine. Construction & demolition waste is rated at variable compressive strength with variable abrasiveness, variable moisture sensitivity and a loose bulk density around 1.20 t/m³. Rebar, timber and plastics make feedstock variability the design driver; a forgiving impact chamber beats an optimised cone. Operator notes from the first month are often the best diagnostic data.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 210 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of 0–4, 4–20, 20–40 mm recycled aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Construction & demolition waste · variable · abrasion variable |
| Design throughput | 210 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | 0–4, 4–20, 20–40 mm recycled aggregate |
| Loose bulk density | 1.20 t/m³ |
| Suggested circuit | mobile impact + magnet + picking → screen |

Why variable feed gradation appears in this circuit
Crusher power draw swings sharply with each loader cycle. In a construction & demolition waste greenfield plant this is usually a system symptom rather than a single machine fault. Most of these problems are diagnosed at the screen, not at the crusher.
- segregation in the stockpile and the dump hopper
- no surge buffer between the loader and the primary feeder
- hard and soft bands are exposed simultaneously at the face
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) sample feed gradation at three points across the belt; 2) record power draw at one-minute intervals; 3) check hopper level alarms and feeder response. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For construction & demolition waste at 210 t/h the working train is mobile impact + magnet + picking → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for construction & demolition waste and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~263 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.20 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 670 kW order-of-magnitude connected load |
The corrective actions for variable feed gradation are applied on top of this base circuit: blend feed from two stockpile faces; add a hopper with level control and a vfd feeder; set the drive power margin for the hardest band, not the average.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 30% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Sample feed gradation at three points across the belt
- Record power draw at one-minute intervals
- Check hopper level alarms and feeder response
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 210 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–4, 4–20, 20–40 mm recycled aggregate |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 670 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for construction & demolition waste, while a verifiable mass balance determines how much lost production actually costs. Most of these problems are diagnosed at the screen, not at the crusher.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 210 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.