Design basis for gabbro greenfield plant
The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. Indicative values are starting points for a design, not guarantees.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 250 t/h of saleable product, with a maximum feed top size near 450 mm and target fractions of railway ballast and concrete aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gabbro · 150–280 MPa · abrasion medium |
| Design throughput | 250 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~450 mm |
| Target product | railway ballast and concrete aggregate |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → 3-deck screen |

Why high energy cost per tonne appears in this circuit
KWh per saleable tonne rises while crusher output stays flat. In a gabbro greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- idling and recirculating material are counted as production
- a grinding circuit is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) install sub-metering on the main drives; 2) calculate specific energy weekly; 3) compare idle time against loaded running hours. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For gabbro at 250 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~313 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~42 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 800 kW order-of-magnitude connected load |
The corrective actions for high energy cost per tonne are applied on top of this base circuit: meter energy against saleable tonnes, not crusher feed; match mill and classifier size to the real d97 target; add vfds to feeders and fans and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 42 mm, a circulating load around 70% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Install sub-metering on the main drives
- Calculate specific energy weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 250 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast and concrete aggregate |
| Crusher setting | CSS measured and logged, ~42 mm starting point |
| Power | Main-drive current at steady feed, 800 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 250 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.