Design basis for gabbro contract crushing
The design basis starts with the rock, not the machine. Gabbro is rated at 150–280 MPa compressive strength with medium abrasiveness, low moisture sensitivity and a loose bulk density around 1.52 t/m³. Dense and tough, so installed power and conveyor sizing deserve a larger margin than a t/h comparison suggests. Operator notes from the first month are often the best diagnostic data.
A contract crushing must relocate between sites with minimal erection time, constrained by short project duration and no permanent foundations. The commercial priority is mobility and fast set-up. For this combination HAMAC works from an indicative design point of 100 t/h of saleable product, with a maximum feed top size near 500 mm and target fractions of railway ballast and concrete aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Gabbro · 150–280 MPa · abrasion medium |
| Design throughput | 100 t/h saleable product (80–200 t/h scenario band) |
| Maximum feed size | ~500 mm |
| Target product | railway ballast and concrete aggregate |
| Loose bulk density | 1.52 t/m³ |
| Suggested circuit | jaw → cone → cone → 3-deck screen |

Why CAPEX justification appears in this circuit
The investment case compares purchase prices instead of lifetime cost. In a gabbro contract crushing this is usually a system symptom rather than a single machine fault. The answer depends on the mass balance, not on a catalogue capacity figure.
- quotes assume different flow sheets and mass balances
- freight, civils, erection and spares are excluded
- availability is assumed at 100% in the payback model
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) request a mass balance with each quotation; 2) confirm the Incoterm and named port; 3) sensitivity-test the payback at 75% utilisation. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For gabbro at 100 t/h the working train is jaw → cone → cone → 3-deck screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for gabbro and for a softer rock. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~125 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.52 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 250 kW order-of-magnitude connected load |
The corrective actions for CAPEX justification are applied on top of this base circuit: normalise every quote to one written flow sheet; include incoterms, civils, erection and a two-year spares package; model annual tonnage as nameplate × hours × realistic utilisation.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 40% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Request a mass balance with each quotation
- Confirm the Incoterm and named port
- Sensitivity-test the payback at 75% utilisation
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 100 t/h nominal |
| Grading | Full sieve analysis, agreed standard, railway ballast and concrete aggregate |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 250 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for gabbro, while mobility and fast set-up determines how much lost production actually costs. The answer depends on the mass balance, not on a catalogue capacity figure.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 100 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.