Design basis for TGM Trapezium Mill grinding dolomite
The design basis starts with the powder, not the mill. Dolomite is a soft–medium mineral at Mohs 3.5 with low moisture sensitivity and specific gravity about 2.8. For a slag grinding for cement the saleable target is aggregate, agricultural lime, filler at D97 20–180 µm. Suits impact crushing and downstream grinding; lime quality depends on the grading. Operator notes from the first month are often the best diagnostic data.
A TGM Trapezium Mill is a sensible starting point for this duty: 2–40 t/h capacity, 40–200 µm fineness range, mid-size powder production for fillers and additives. For this combination HAMAC works from an indicative design point of 10 t/h of saleable powder, with a maximum feed size near 25 mm and a target D97 of 20–180. Compare cost per saleable tonne over the plant life.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Dolomite · Mohs 3.5 · soft–medium · SG 2.8 |
| Design throughput | 10 t/h saleable powder (10–60 t/h scenario band) |
| Target fineness | D97 20–180 µm |
| Maximum feed size | ~25 mm |
| Mill type | TGM Trapezium Mill |
| Suggested line | impact crusher → screen → optional Raymond mill |

Why high energy cost per tonne of powder appears in this grinding circuit
KWh per tonne of powder rises while mill output stays flat. In a TGM Trapezium Mill circuit on dolomite this is usually a system symptom across the mill, classifier and collector rather than a single machine fault. Start from the product specification and work backwards to the feed.
- idling and recirculating material are counted as production
- the mill is oversized for the required fineness
- drives run at fixed speed regardless of feed rate
Measurements are only comparable when the sieve standard is the same. Before changing a mill setting, check these in order: 1) install sub-metering on the main grinding drives; 2) calculate specific energy per tonne weekly; 3) compare idle time against loaded running hours. Agree the acceptance test and sampling method before the order is placed.
Recommended grinding configuration
For dolomite at 10 t/h the working line is impact crusher → screen → optional Raymond mill. The TGM Trapezium Mill sits at the centre; a dynamic air classifier sets the cut and a pulse-jet bag filter holds the system under negative pressure so the finished powder stays clean. Operator notes from the first month are often the best diagnostic data.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Weigh / belt feeder, VFD control, ~12 t/h design margin |
| Milling | TGM Trapezium Mill, 2–40 t/h, 40–200 µm |
| Classification | Dynamic air classifier, rotor speed tuned to target D97 20–180 |
| Collection | Pulse-jet bag filter, negative pressure, ~12 m³/min air volume |
| Conveying / air | Centrifugal fan and ducting sized for 12 m³/min total air |
| Control | Interlocked start-up, load-based feed trim, ~140 kW connected load |
The corrective actions for high energy cost per tonne of powder are applied on top of this base circuit: meter energy against saleable tonnes of powder; match mill and classifier size to the real d97 target; add vfds to feeders, fans and the mill and interlock them with feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after any liner, rotor or media change. For this circuit the starting point is a classifier rotor speed that holds D97 20–180, a circulating load around 55% and a collection efficiency above 99%. Measurements are only comparable when the sieve standard is the same.
- Install sub-metering on the main grinding drives
- Calculate specific energy per tonne weekly
- Compare idle time against loaded running hours
| Parameter | Indicative value / method |
|---|---|
| Fineness | Laser diffraction / sieve, target D97 20–180, agreed standard |
| Capacity | Weighed saleable powder per shift, 10 t/h nominal |
| Moisture | Feed and product moisture each shift |
| Power | Main drive current at steady feed, ~140 kW connected load |
| Purity | Brightness / Fe content batch check for white fillers |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, mill setting and classifier efficiency.
Cost, risk and what to confirm in writing
Compare this grinding plant as cost per tonne of saleable powder, not purchase price. Energy, wear parts, media and downtime dominate the operating cost for dolomite, while energy per tonne determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 55% return / circulating load.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 10 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the fineness test method (laser diffraction vs. sieve), sampling point and acceptance test before the order is placed.
Operator notes from the first month are often the best diagnostic data. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target fineness and capacity to HAMAC Machinery for a comparable configuration and budget.
