Design basis for andesite remote site
The design basis starts with the rock, not the machine. Andesite is rated at 120–240 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.44 t/m³. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. A change in one stage changes the circulating load in all the others.
A remote site must run with limited grid power and a long spares lead time, constrained by diesel generation and infrequent service visits. The commercial priority is energy and spares autonomy. For this combination HAMAC works from an indicative design point of 60 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of asphalt aggregate, 0–5, 5–16 mm.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Andesite · 120–240 MPa · abrasion medium–high |
| Design throughput | 60 t/h saleable product (60–180 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | asphalt aggregate, 0–5, 5–16 mm |
| Loose bulk density | 1.44 t/m³ |
| Suggested circuit | jaw → cone → VSI → screen |

Why start-up instability appears in this circuit
The plant cannot hold a steady feed during its first weeks. In a andesite remote site this is usually a system symptom rather than a single machine fault. On site, feed variability hides problems that a test sample never shows.
- interlocks and feeder ramp rates were never tuned together
- settings were changed without a commissioning log
- operators were trained on a different circuit
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) verify every interlock in no-load and loaded runs; 2) sign off the settings log with both parties; 3) repeat a full sieve analysis after the first 100 hours. Ask for the mass balance and the test method behind any quoted number.
Recommended equipment configuration
For andesite at 60 t/h the working train is jaw → cone → VSI → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for andesite and for a softer rock. A change in one stage changes the circulating load in all the others.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~75 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.44 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 130 kW order-of-magnitude connected load |
The corrective actions for start-up instability are applied on top of this base circuit: ramp feed in defined steps and record power at each step; freeze a signed settings log at handover; train operators on the actual flow sheet with a written checklist.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 20% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Verify every interlock in no-load and loaded runs
- Sign off the settings log with both parties
- Repeat a full sieve analysis after the first 100 hours
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 60 t/h nominal |
| Grading | Full sieve analysis, agreed standard, asphalt aggregate, 0–5, 5–16 mm |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 130 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Ask for the mass balance and the test method behind any quoted number. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for andesite, while energy and spares autonomy determines how much lost production actually costs. On site, feed variability hides problems that a test sample never shows.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 60 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
A change in one stage changes the circulating load in all the others. Ask for the mass balance and the test method behind any quoted number. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.