● Crushing & grinding equipment · Since 2004
Equipment
Wheel Type Mobile CrushersTracked Crushing PlantsCone CrusherJaw CrusherImpact CrusherGrinding MillsModular Crushing PlantSupporting EquipmentsSand Making & Washing
Solutions
All solutionsEngineering solutions (700)Circuit designGrinding & mineralsProjectsMarkets
Company
About HAMACResourcesIndustry glossaryBlogFAQWear partsContact
Wear & service

Andesite quarry expansion: Excessive liner consumption — solution & design basis

Liner sets are replaced far more often than the budget assumed — a 170 t/h design basis, configuration and acceptance checks.

Andesite quarry expansion with excessive liner consumption is normally resolved by checking the circuit against the saleable product specification first: select manganese grade against measured silica content. For a 170 t/h design point on andesite, HAMAC would review jaw → cone → VSI → screen, then confirm the settings with a written acceptance test. Written acceptance criteria prevent a dispute turning into a redesign.

170 t/hindicative design point
120–240 MPacompressive strength
150–300 t/hscenario capacity band
500 kWorder-of-magnitude installed power
Key takeaways
  1. Andesite is medium–high in abrasiveness and low in moisture sensitivity; Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification.
  2. For quarry expansion the priority is throughput continuity, constrained by a shared feed point and limited stockpile area.
  3. Excessive liner consumption typically appears as: liner sets are replaced far more often than the budget assumed.
  4. First corrective action: select manganese grade against measured silica content.
  5. All values are nominal; confirm them in a written proposal with a defined test method.

Design basis for andesite quarry expansion

The design basis starts with the rock, not the machine. Andesite is rated at 120–240 MPa compressive strength with medium–high abrasiveness, low moisture sensitivity and a loose bulk density around 1.44 t/m³. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. Indicative values are starting points for a design, not guarantees.

A quarry expansion must add saleable output without stopping the existing line, constrained by a shared feed point and limited stockpile area. The commercial priority is throughput continuity. For this combination HAMAC works from an indicative design point of 170 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of asphalt aggregate, 0–5, 5–16 mm.

Andesite — design basis (nominal values)
ParameterIndicative value / method
Raw materialAndesite · 120–240 MPa · abrasion medium–high
Design throughput170 t/h saleable product (150–300 t/h scenario band)
Maximum feed size~600 mm
Target productasphalt aggregate, 0–5, 5–16 mm
Loose bulk density1.44 t/m³
Suggested circuitjaw → cone → VSI → screen
Andesite quarry expansion — Design basis for andesite quarry expansion — HAMAC impact crusher
Andesite quarry expansion — Design basis for andesite quarry expansion — HAMAC impact crusher reference.

Why excessive liner consumption appears in this circuit

Liner sets are replaced far more often than the budget assumed. In a andesite quarry expansion this is usually a system symptom rather than a single machine fault. Written acceptance criteria prevent a dispute turning into a redesign.

  • the alloy does not match feed abrasiveness
  • the crusher is running with a worn chamber profile
  • tramp metal is reaching the chamber

The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) weigh each liner set before and after use; 2) calculate cost per saleable tonne; 3) photograph the chamber at every change-out. Agree the acceptance test and sampling method before the order is placed.

Recommended equipment configuration

For andesite at 170 t/h the working train is jaw → cone → VSI → screen. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for andesite and for a softer rock. Indicative values are starting points for a design, not guarantees.

Indicative stage configuration
ParameterIndicative value / method
FeedingVibrating grizzly feeder, VFD control, ~213 t/h design margin
Primary reductionJaw / impact crusher, nominal CSS ~26 mm at the secondary stage
Secondary / tertiarycone
ScreeningMulti-deck screen sized for 40% circulating load
ConveyingBelts sized for fresh feed + return stream, 1.44 t/m³ bulk density
ControlInterlocked start-up, power-based feed trim, 500 kW order-of-magnitude connected load

The corrective actions for excessive liner consumption are applied on top of this base circuit: select manganese grade against measured silica content; rotate or replace liners before the profile is lost; install a magnet and metal detector on the feed belt.

Andesite quarry expansion — Recommended equipment configuration — HAMAC impact crusher
Andesite quarry expansion — Recommended equipment configuration — HAMAC impact crusher reference.

Operating settings and acceptance checks

Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 40% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.

  • Weigh each liner set before and after use
  • Calculate cost per saleable tonne
  • Photograph the chamber at every change-out
Acceptance checks to write into the contract
ParameterIndicative value / method
CapacityMeasured over a full shift, saleable tonnes, 170 t/h nominal
GradingFull sieve analysis, agreed standard, asphalt aggregate, 0–5, 5–16 mm
Crusher settingCSS measured and logged, ~26 mm starting point
PowerMain-drive current at steady feed, 500 kW connected load
WearLiner mass before and after, cost per saleable tonne

Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.

Cost, risk and what to confirm in writing

Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for andesite, while throughput continuity determines how much lost production actually costs. Written acceptance criteria prevent a dispute turning into a redesign.

  • Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
  • State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
  • Model annual output as 170 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
  • Agree the sampling method, sieve standard and acceptance test before the order is placed.

Indicative values are starting points for a design, not guarantees. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.

Andesite quarry expansion — Cost, risk and what to confirm in writing — HAMAC impact crusher
Andesite quarry expansion — Cost, risk and what to confirm in writing — HAMAC impact crusher reference.
FAQ

Andesite quarry expansion — questions answered

Direct answers to the questions buyers ask most often.

What causes excessive liner consumption in a andesite quarry expansion?

Liner sets are replaced far more often than the budget assumed. The usual causes are the alloy does not match feed abrasiveness; the crusher is running with a worn chamber profile; tramp metal is reaching the chamber. select manganese grade against measured silica content.

Which crusher train suits andesite at 150–300 t/h?

A typical configuration is jaw → cone → VSI → screen. Good cubicity after a VSI shaping pass; consistent choke feed is needed to hold the flakiness index within the asphalt specification. The final list depends on feed gradation, moisture, product fractions and local power and space limits.

What should be confirmed before ordering a 170 t/h plant?

A written flow sheet and mass balance, the product grading standard, CSS and screen media, installed power and starting method, the Incoterm and named port, a spares list, and an acceptance test with a defined sampling method. All published figures are nominal.

Request a quotation

Tell us what you need

A short message is enough. A HAMAC engineer replies with a flow sheet and budget within 24 hours.

Ask an engineer about this configuration

Two fields are enough. An engineer replies with a flow sheet and budget within 24 hours.

Not sure what to write? Tap what fits. optional · one tap each
Material
Target capacity
We only use your details to answer this enquiry. Privacy Policy
✆

WhatsApp / Mobile

+86-151-3623-6223
☎
⌖

Factory & headquarters

No. 57 Kexue Avenue, National Hi-Tech Industrial Development Zone, Zhengzhou, Henan, China

⏱

Response time

Technical reply within 24 hours, Monday to Saturday.

Have the feed data for your own site?

Send material, maximum feed size, target t/h and required fractions — a HAMAC engineer will return a written flow sheet and budget.

WhatsApp Get a quote Call