Design basis for talc greenfield plant
The design basis starts with the rock, not the machine. Talc is rated at 10–30 MPa compressive strength with very low abrasiveness, low moisture sensitivity and a loose bulk density around 1.30 t/m³. Very soft and plate-like; over-grinding and heat build-up are the main risks in the mill. Measurements are only comparable when the sieve standard is the same.
A greenfield plant must fix the entire flow sheet before civil works begin, constrained by an untested feed gradation and a fixed commissioning date. The commercial priority is a verifiable mass balance. For this combination HAMAC works from an indicative design point of 250 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of fine powder for plastics and coatings.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Talc · 10–30 MPa · abrasion very low |
| Design throughput | 250 t/h saleable product (200–400 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | fine powder for plastics and coatings |
| Loose bulk density | 1.30 t/m³ |
| Suggested circuit | impact → grinding mill → air classifier |

Why unplanned downtime appears in this circuit
Short stops accumulate into a large annual output loss. In a talc greenfield plant this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- no planned change-out window for wear parts
- spares with long lead times are not held on site
- interlock and lubrication faults are cleared without root-cause logging
Operator notes from the first month are often the best diagnostic data. Before changing a crusher setting, check these in order: 1) report availability and utilisation separately each month; 2) review the top five stop causes; 3) verify spares stock against the recommended list. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For talc at 250 t/h the working train is impact → grinding mill → air classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for talc and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~313 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~30 mm at the secondary stage |
| Secondary / tertiary | grinding mill |
| Screening | Multi-deck screen sized for 70% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.30 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 740 kW order-of-magnitude connected load |
The corrective actions for unplanned downtime are applied on top of this base circuit: schedule liner changes by measured wear rate, not by calendar; hold a recommended spares list for the first two years; log every stop with a fault code and a corrective action.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 30 mm, a circulating load around 70% and a screen efficiency target above 90%. Operator notes from the first month are often the best diagnostic data.
- Report availability and utilisation separately each month
- Review the top five stop causes
- Verify spares stock against the recommended list
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 250 t/h nominal |
| Grading | Full sieve analysis, agreed standard, fine powder for plastics and coatings |
| Crusher setting | CSS measured and logged, ~30 mm starting point |
| Power | Main-drive current at steady feed, 740 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for talc, while a verifiable mass balance determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 70% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 250 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.