Overview
Buying a Spiral (Screw) Sand Washer direct from HAMAC removes the trading margin and gives you engineering support from enquiry to commissioning.

Why buy direct
- One project manager for the whole order.
- Workshop assembly, test and container loading plan.
- Flow-sheet design, layout and foundation reference.
- Installation supervision, training and 24h technical response.
Export & documentation
Quoted FOB / CFR / CIF. Documentation applicable to your market (CE where required), Spanish manuals for LatAm, motors set to local voltage.
How to order
Send project data → receive design + budget in 24h → refine drawings → manufacture → install.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Spiral (Screw) Sand Washer |
| Category | Sand Making & Washing |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | three-year view |
These values are the starting point for a written proposal on spiral (screw) sand washer; they are nominal and should be confirmed against a sample test before manufacture.
Published Spiral (Screw) Sand Washer model data
| Model | Screw diameter (mm) | Sink length (mm) | Feeding size (mm) | Capacity (t/h) | Power (kW) |
|---|---|---|---|---|---|
| XL515 | 515 | 7615 | ≤10 | 5–15 | 5.5 |
| XL765 | 765 | 7620 | ≤10 | 20–60 | 11 |
| XL920 | 920 | 7585 | ≤10 | 40–110 | 11 |
| 2XL920 | 920 | 7585 | ≤10 | 80–220 | 2×11 |
| XL1120 | 1120 | 9750 | ≤10 | 50–130 | 18.5 |
| 2XL1120 | 1120 | 9750 | ≤10 | 100–260 | 2×18.5 |
XL / 2XL screw sand washers, 5–260 t/h, remove clay and fines from manufactured sand with low water consumption. Read the table column by column against cement raw-meal preparation: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | simple operator maintenance |
| Evaluation horizon | three-year view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for spiral (screw) sand washer may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Review the crusher chamber profile with the liner supplier against the feed material.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Control system language, telemetry and remote diagnostics availability.
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Whether the quoted t/h is achieved at cement raw-meal preparation or under ideal laboratory feed.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Decommissioning or relocation value at the end of a three-year horizon.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
Ask each supplier to price the same list. Quotations for spiral (screw) sand washer only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Letting the cement raw-meal preparation duty be defined verbally instead of in the contract.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying simple operator maintenance on price alone and losing it in availability.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure noise and dust at the operator position against the local limit.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Confirm the direction and tension of every belt under no load.
- Sample each product fraction and compare with the specification.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Verify rotation direction on every motor before coupling.
The commissioning record becomes the reference for every liner change in the three-year plan.