Overview
The Symons Cone Crusher is offered across several model sizes. Price depends on capacity, wear-package grade, mobility (stationary, wheel or tracked) and the level of automation, not on a single list price.

What drives the price
- Model size and rated capacity — larger rotors / chambers cost more.
- Mobility: stationary < wheel-mounted < tracked (tracked adds hydraulic & engine cost).
- Motor specification and starter (soft-start / VFD) and local voltage.
- Wear-parts grade (Mn13 / Mn18 / Mn22 / high-chrome) and spare-parts package.
- Control system: relay panel vs PLC with remote monitoring.
Typical price brackets
Entry models for contractor use start in the low five-figure USD range; mid-size export configurations are typically six-figure; large tracked or fully automated lines are higher. Exact numbers depend on the technical specification — request a written quotation rather than a ballpark.
How to get an accurate quote
Send material, feed size, target t/h and product sizes. HAMAC returns a flow sheet, equipment list and FOB / CFR / CIF price within 24 hours.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Symons Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | ten-year view |
Use the table as a checklist when comparing quotations for symons cone crusher — a lower price often means one of these parameters was quietly reduced.
Published Symons Cone Crusher model data
| Model | SCC 3’ | SCC 4 1/4’ | SCC 5 1/2’ | SCC 7’ |
|---|---|---|---|---|
| Dia. | 900 mm (3’) | 1295 mm (4 1/4’) | 1650 mm (5 1/2’) | 2134 mm (7’) |
| Fine Closing Side | 83 mm | 109 mm | 188 mm | 253 mm |
| Fine Open Side | 102 mm | 137 mm | 209 mm | 278 mm |
| Medium Closing Side | 159 mm | 188 mm | 213 mm | 303 mm |
| Medium Open Side | 175 mm | 210 mm | 241 mm | 334 mm |
| Coarse Closing Side | 159 mm | 216 mm | 241 mm | 334 mm |
| Coarse Open Side | 175 mm | 241 mm | 268 mm | 369 mm |
| Outlet Setting | 9-22 mm | 13-38 mm | 16-38 mm | 19-38 mm |
S series Symons cone crusher is a kind of high efficiency cone crusher, which integrate optimization of cavity-type and reasonable stroke and advanced technology, and the conception of. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | minimal civil works |
| Evaluation horizon | ten-year view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for symons cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
Shortening this sequence is possible on a brownfield extension, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Local service partner, technician travel time and visa requirements for your market.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Closed-side setting range and whether automatic setting regulation is included.
- Choke-feed arrangement: surge bin, feeder control and level indication.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Using one liner profile for both secondary and tertiary stages.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Verify rotation direction on every motor before coupling.
- Measure and log the as-new CSS / setting for future wear comparison.
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Sample each product fraction and compare with the specification.
- Confirm the direction and tension of every belt under no load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
Keep the signed record; it is the only defensible baseline for later performance disputes.