Overview
Choosing a Screw Type Sand Washing Machine starts with the rock and the target product, not a catalogue number. The steps below turn your project data into a defensible model choice.

1. Start with the material
- Hard, abrasive rock (granite, basalt, quartz): compression crushing, premium Mn liners.
- Soft rock (limestone, marble, dolomite): impact crushing for shape at lower cost.
- High silica (river pebble, quartz): plan VSI + wear budget.
2. Size to saleable t/h
Add 10–20% surge to nameplate capacity; undersizing is a permanent bottleneck, oversizing wastes capital.
3. Match the product grading
Product size and shape (flakiness index) decide chamber and screen deck setup.
Pre-order checklist
- Feed size and max lump.
- Required t/h and product fractions.
- Site power (voltage / frequency) and mobility need.
- Local standards (CE, GOST, etc.).
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Screw Type Sand Washing Machine |
| Category | Supporting Equipments |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for screw type sand washing machine cannot be compared on scope.
Published Screw Type Sand Washing Machine model data
| Model | Diameter of spiral (mm) | Width of washing tank (mm) | Feeding size (mm) | Spiral rotation speed (r/min) |
|---|---|---|---|---|
| LXS-515 | 515 | 6715 | ≤10 | 38 |
| LXS-765 | 765 | 7620 | ≤10 | 26 |
| LXS-915 | 915 | 7650 | ≤10 | 21 |
| LXS-1115 | 1115 | 9782 | ≤10 | 17 |
| 2LXS-915 | 915 | 7650 | ≤10 | 21 |
| 2LXS-1115 | 1115 | 9782 | ≤10 | 17 |
The high-efficiency screw type sand washing machine is widely used in industries such as highways and hydropower to clean, dewater, and grade sand and gravel materials. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | five-year view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for screw type sand washing machine may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.

From enquiry to the first saleable tonne
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.
What to verify before you sign
- Wear-part interchangeability across machines in the same circuit.
- Closed-side setting range and whether automatic setting regulation is included.
- Dust and noise control designed to the local emission limits for your market.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Local service partner, technician travel time and visa requirements for your market.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Guaranteed power draw and the maximum mechanical availability trade-off it implies.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Check belt tracking, chute build-up and transfer-point dust.
- Dry-run the plant empty for the specified period and record vibration.
- Record power draw, tonnage and chamber pressure at steady state.
- Confirm the direction and tension of every belt under no load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify rotation direction on every motor before coupling.
For a full-time plant team, run through this list twice — once with the supervisor and once without.