Overview
Choosing a Mobile 3 In 1 Crushing & Screening Plant starts with the rock and the target product, not a catalogue number. The steps below turn your project data into a defensible model choice.

1. Start with the material
- Hard, abrasive rock (granite, basalt, quartz): compression crushing, premium Mn liners.
- Soft rock (limestone, marble, dolomite): impact crushing for shape at lower cost.
- High silica (river pebble, quartz): plan VSI + wear budget.
2. Size to saleable t/h
Add 10–20% surge to nameplate capacity; undersizing is a permanent bottleneck, oversizing wastes capital.
3. Match the product grading
Product size and shape (flakiness index) decide chamber and screen deck setup.
Pre-order checklist
- Feed size and max lump.
- Required t/h and product fractions.
- Site power (voltage / frequency) and mobility need.
- Local standards (CE, GOST, etc.).
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Mobile 3 In 1 Crushing & Screening Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | seven-year view |
At high-tonnage aggregate supply, the ranking of these parameters changes: lowest energy per tonne usually becomes the deciding constraint rather than the headline tonnage.
Published Mobile 3 In 1 Crushing & Screening Plant model data
| Model | Vibrating feeder | Impact crusher | Vibrating screen | Main belt | Capacity (t/h) |
|---|---|---|---|---|---|
| K3-PF1214-3C | GZD1142 | PFV1214 | 3YK1848 | B1000 | 100–200 |
| K3-LF150-3C | GZD9638 | LF150 | 3YK1548 | B800 | 80–150 |
| K3-LF250-3C | GZD1142 | LF250 | 3YK1848 | B1000 | 150–300 |
Feeding, crushing and screening on one wheel chassis — 80–300 t/h — for contractors who need a complete plant with minimal setup. Read the table column by column against high-tonnage aggregate supply: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | seven-year view |
| Site condition | a greenfield site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for mobile 3 in 1 crushing & screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.

From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Book shipping, prepare the packing list and confirm the container loading plan.
Shortening this sequence is possible on a greenfield site, but only where the feed and product specification are already fully defined.
What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Closed-side setting range and whether automatic setting regulation is included.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the seven-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
A seven-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Using one liner profile for both secondary and tertiary stages.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check belt tracking, chute build-up and transfer-point dust.
- Sample each product fraction and compare with the specification.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record power draw, tonnage and chamber pressure at steady state.
- Measure noise and dust at the operator position against the local limit.
- Record the baseline grading curve for each product fraction.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check lubrication levels, grease lines and oil cooler operation.
The commissioning record becomes the reference for every liner change in the seven-year plan.