Overview
The Mobile 4 In 1 Crushing & Screening Plant is applied across aggregates, mining, beneficiation and recycling. The material properties decide whether it is the right machine.

Materials it handles
- Hard rock: granite, basalt, andesite, gabbro.
- Soft rock: limestone, marble, dolomite.
- Ores: iron, copper, gold, manganese.
- Recycling: concrete, asphalt, C&D waste.
Industries
- Quarrying and construction aggregates.
- Metal ore crushing and beneficiation.
- Manufactured sand and road base.
- Cement raw meal and industrial minerals.
Typical configuration
Usually combined with a feeder, screen and conveyors into a complete circuit, or as a module in a mobile plant.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Mobile 4 In 1 Crushing & Screening Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for mobile 4 in 1 crushing & screening plant cannot be compared on scope.
Published Mobile 4 In 1 Crushing & Screening Plant model data
| Model | Vibrating Feeder | Jaw Crusher | Cone Crusher / Impact Crusher | Vibrating Screen |
|---|---|---|---|---|
| Y3SY9E46 | GZD850×3000 | PE400×600 | PYB900 | 3YZS1237 |
| Y3SC75E57 | GZD850×3000 | PE500×700 | 3FT | 3YZS1548 |
| Y3SF1210E57 | GZD850×3000 | PE500×700 | PF1210 | 3YZS1548 |
| Y2SY9E57 | GZD850×3000 | PE500×700 | PYB900 | 2YZS1237 |
| Y3SF1010E46 | GZD850×3000 | PE400×600 | PF1010 | 3YZS1237 |
The 4-in-1 Mobile Crushing Plant combines a vibrating feeder, jaw crusher, cone or impact crusher, and vibrating screen in a single frame, offering an economical solution for mobile crushing. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | strict product cubicity |
| Evaluation horizon | five-year view |
| Site condition | a coastal export terminal |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for mobile 4 in 1 crushing & screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Book shipping, prepare the packing list and confirm the container loading plan.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
For an owner-operator team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for your market.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Dust and noise control designed to the local emission limits for your market.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Closed-side setting range and whether automatic setting regulation is included.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Model a low, base and high case for tonnes per liner set. The spread tells you more than a single optimistic estimate.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying strict product cubicity on price alone and losing it in availability.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
For mine pre-beneficiation feed, protect the strict product cubicity requirement explicitly in the contract documents.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Measure and log the as-new CSS / setting for future wear comparison.
- Verify rotation direction on every motor before coupling.
- Check belt tracking, chute build-up and transfer-point dust.
- Sample each product fraction and compare with the specification.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Calibrate the belt scale and any level probes against a known load.
On a coastal export terminal, allow extra time for the dust and noise measurements.