Overview
Practical, numbers-first guidance on the Mobile 3 In 1 Crushing & Screening Plant — written for engineers specifying, buying and running crushing plants.

How it compares
- Primary reduction vs a gyratory for very high tonnage.
- Compression (cone) vs impact for shape vs wear.
- Mobile vs stationary for your site.
When to pick this machine
Mobile 3 In 1 Crushing & Screening Plant is chosen when its reduction mechanism and capacity match your material and product spec.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | Mobile 3 In 1 Crushing & Screening Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | single-project view |
Treat this as a living sheet. Every revision of the flow sheet for your market should update the same fields so the equipment list stays traceable.
Published Mobile 3 In 1 Crushing & Screening Plant model data
| Model | Vibrating feeder | Impact crusher | Vibrating screen | Main belt | Capacity (t/h) |
|---|---|---|---|---|---|
| K3-PF1214-3C | GZD1142 | PFV1214 | 3YK1848 | B1000 | 100–200 |
| K3-LF150-3C | GZD9638 | LF150 | 3YK1548 | B800 | 80–150 |
| K3-LF250-3C | GZD1142 | LF250 | 3YK1848 | B1000 | 150–300 |
Feeding, crushing and screening on one wheel chassis — 80–300 t/h — for contractors who need a complete plant with minimal setup. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | simple operator maintenance |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for mobile 3 in 1 crushing & screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.

What to verify before you sign
- Nameplate data for local voltage, frequency and the applicable conformity scheme.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Control system language, telemetry and remote diagnostics availability.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Product sampling points and the lab equipment needed for routine grading checks.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Decommissioning or relocation value at the end of a single-project horizon.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Buying simple operator maintenance on price alone and losing it in availability.
For contract crushing on short-term sites, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm the direction and tension of every belt under no load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Check belt tracking, chute build-up and transfer-point dust.
- Dry-run the plant empty for the specified period and record vibration.
- Verify rotation direction on every motor before coupling.
- Sample each product fraction and compare with the specification.
Keep the signed record; it is the only defensible baseline for later performance disputes.