Overview
Practical, numbers-first guidance on the HCS Hydraulic Cone Crusher — written for engineers specifying, buying and running crushing plants.

Preparation
- Confirm foundation per HAMAC layout.
- Check power and cable routing.
- Lift and level on grout.
Commissioning
- Dry run, then graded load.
- Set CSS and verify product.
- Train operators.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Machine line | HCS Hydraulic Cone Crusher |
| Category | Cone Crusher |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | ten-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Published HCS Hydraulic Cone Crusher model data
| Model | Cavity | Feed opening | Min opening | Capacity | Maximum Power |
|---|---|---|---|---|---|
| HST100 | S1(EC) | 240 mm | 22 mm | 85-170 t/h | 90 kW |
| S2(MC) | 200 mm | 19 mm | 70-130 t/h | ||
| H1(F) | 135 mm | 10 mm | 45-115 t/h | ||
| H2(MF) | 65 mm | 8 mm | 35-80 t/h | ||
| H3(UF) | 35 mm | 4 mm | 27-60 t/h | ||
| HST160 | S1(EC) | 360 mm | 25 mm | 120-345 t/h | 160 kW |
| S2(MC) | 300 mm | 22 mm | 105-305 t/h | ||
| S3(C) | 235 mm | 19 mm | 90-275 t/h |
HST single cylinder hydraulic cone crusher integrates mechanical, hydraulic, electrical, automation, intelligent control and other technologies, and can be widely used in medium, fine and. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a brownfield extension |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for hcs hydraulic cone crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
On contract crushing on short-term sites, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for your market.
- Guaranteed power draw and the lowest cost per tonne trade-off it implies.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
On contract crushing on short-term sites, the lowest cost per tonne objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm all guards, emergency stops and pull-wire switches function.
- Calibrate the belt scale and any level probes against a known load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Dry-run the plant empty for the specified period and record vibration.
The commissioning record becomes the reference for every liner change in the ten-year plan.