Overview
A turnkey contract covers the flow sheet, manufacture, shipment to Hamburg, civil reference drawings, erection supervision, commissioning and operator training — one project manager from enquiry to hand-over.

Scope of supply
- Site survey and material testing.
- Flow sheet, layout and foundation reference.
- Manufacture, workshop assembly and load test.
- Freight and customs documentation for Germany.
- Erection supervision, 400V 50Hz power tie-in and training.
Market parameters for Germany
| Item | Reference |
|---|---|
| Region | Europe |
| Port | Hamburg |
| Voltage / frequency | 400V 50Hz |
| Standards | DIN EN |
| Typical feed | Limestone, Recycling |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Hamburg |
| Site supply | 400V 50Hz |
| Local standards | DIN EN |
| Region | Europe |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | ten-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | ten-year view |
| Site condition | a confined urban yard |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Specify motors, starters and documentation for 400V 50Hz and DIN EN before manufacture.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
Shortening this sequence is possible on a confined urban yard, but only where the feed and product specification are already fully defined.
What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Product sampling points and the lab equipment needed for routine grading checks.
- Availability of a mixed local and expatriate team for liner changes and the lifting equipment on site.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Wear-part interchangeability across machines in the same circuit.
For contract crushing on short-term sites, give the maximum mechanical availability line extra weight; a generic checklist will not rank the offers correctly.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to Germany is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Check lubrication levels, grease lines and oil cooler operation.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Measure noise and dust at the operator position against the local limit.
- Calibrate the belt scale and any level probes against a known load.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
For a mixed local and expatriate team, run through this list twice — once with the supervisor and once without.