Overview
HAMAC supplies crushing and grinding equipment to South Korea, shipped to Busan and quoted to local standards (KS). Power is configured for 380V 60Hz.

Crushing equipment for South Korea
- Popular material: Limestone, Granite.
- Destination port: Busan.
- Voltage / frequency: 380V 60Hz.
- Standards: KS.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 380V 60Hz and KS.
- FOB / CFR / CIF quotation to Busan.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for South Korea, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Busan |
| Site supply | 380V 60Hz |
| Local standards | KS |
| Region | Asia |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | seven-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | fast mobilisation |
| Evaluation horizon | seven-year view |
| Site condition | an existing quarry bench |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
On seasonal road-project supply, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Local service partner, technician travel time and visa requirements for South Korea.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Product sampling points and the lab equipment needed for routine grading checks.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Decommissioning or relocation value at the end of a seven-year horizon.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On seasonal road-project supply, the fast mobilisation objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Using one liner profile for both secondary and tertiary stages.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
On an existing quarry bench, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Measure noise and dust at the operator position against the local limit.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Confirm all guards, emergency stops and pull-wire switches function.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Calibrate the belt scale and any level probes against a known load.
- Measure and log the as-new CSS / setting for future wear comparison.
The commissioning record becomes the reference for every liner change in the seven-year plan.