Overview
Practical notes for bringing a HAMAC crushing or grinding plant into UAE, from quotation to commissioning.

Shipping & port
- Destination: Jebel Ali.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 415V 50Hz.
- Standards: ESMA.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for UAE customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Jebel Ali |
| Site supply | 415V 50Hz |
| Local standards | ESMA |
| Region | Middle East |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | five-year view |
Treat this as a living sheet. Every revision of the flow sheet for UAE should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | simple operator maintenance |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Book container or flat-rack space to Jebel Ali and prepare the customs document set in advance.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
For an owner-operator team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Decommissioning or relocation value at the end of a five-year horizon.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Closed-side setting range and whether automatic setting regulation is included.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Overlooking dust, noise and water permits in UAE until erection has already started.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Buying simple operator maintenance on price alone and losing it in availability.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Check lubrication levels, grease lines and oil cooler operation.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm all guards, emergency stops and pull-wire switches function.
- Measure noise and dust at the operator position against the local limit.
- Measure and log the as-new CSS / setting for future wear comparison.
- Confirm the direction and tension of every belt under no load.
The commissioning record becomes the reference for every liner change in the five-year plan.