Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Tunisia, from quotation to commissioning.

Shipping & port
- Destination: Tunis.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 380V 50Hz.
- Standards: NT.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Tunisia customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Tunis |
| Site supply | 380V 50Hz |
| Local standards | NT |
| Region | Africa |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | strict product cubicity |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Specify motors, starters and documentation for 380V 50Hz and NT before manufacture.
- Plan training for a small contractor crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Control system language, telemetry and remote diagnostics availability.
- Wear-part interchangeability across machines in the same circuit.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Local service partner, technician travel time and visa requirements for Tunisia.
- Closed-side setting range and whether automatic setting regulation is included.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On contract crushing on short-term sites, the strict product cubicity objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Buying strict product cubicity on price alone and losing it in availability.
- Overlooking dust, noise and water permits in Tunisia until erection has already started.
For contract crushing on short-term sites, protect the strict product cubicity requirement explicitly in the contract documents.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check belt tracking, chute build-up and transfer-point dust.
- Calibrate the belt scale and any level probes against a known load.
- Verify rotation direction on every motor before coupling.
- Confirm the direction and tension of every belt under no load.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
The commissioning record becomes the reference for every liner change in the five-year plan.