Overview
Practical notes for bringing a HAMAC crushing or grinding plant into South Africa, from quotation to commissioning.

Shipping & port
- Destination: Durban.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 380V 50Hz.
- Standards: SANS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for South Africa customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Durban |
| Site supply | 380V 50Hz |
| Local standards | SANS |
| Region | Africa |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on the crushing and screening plant; they are nominal and should be confirmed against a sample test before manufacture.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | strict product cubicity |
| Evaluation horizon | five-year view |
| Site condition | a greenfield site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Specify motors, starters and documentation for 380V 50Hz and SANS before manufacture.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Decommissioning or relocation value at the end of a five-year horizon.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Local service partner, technician travel time and visa requirements for South Africa.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Nameplate data for 380V 50Hz and the SANS certificate set.
These are the items HAMAC puts in the technical proposal; if another offer is silent on them, ask why.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to South Africa is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Dry-run the plant empty for the specified period and record vibration.
- Measure noise and dust at the operator position against the local limit.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Measure and log the as-new CSS / setting for future wear comparison.
- Record the baseline grading curve for each product fraction.
- Check belt tracking, chute build-up and transfer-point dust.
- Record power draw, tonnage and chamber pressure at steady state.
Keep the signed record; it is the only defensible baseline for later performance disputes.