Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Papua New Guinea, from quotation to commissioning.

Shipping & port
- Destination: Lae.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 415V 50Hz.
- Standards: PNGS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Papua New Guinea customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Lae |
| Site supply | 415V 50Hz |
| Local standards | PNGS |
| Region | Oceania |
| Assumed duty | seasonal road-project supply |
| Evaluation horizon | five-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | seasonal road-project supply |
| Primary objective | minimal civil works |
| Evaluation horizon | five-year view |
| Site condition | a confined urban yard |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Review the crusher chamber profile with the liner supplier against the feed material.
A realistic programme reserves time for permits, foundation curing and shipping to Papua New Guinea before any steel is cut.

What to verify before you sign
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Dust and noise control designed to the local emission limits for Papua New Guinea.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Decommissioning or relocation value at the end of a five-year horizon.
- Nameplate data for 415V 50Hz and the PNGS certificate set.
- Product sampling points and the lab equipment needed for routine grading checks.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For the crushing and screening plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Letting the seasonal road-project supply duty be defined verbally instead of in the contract.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Using one liner profile for both secondary and tertiary stages.
For seasonal road-project supply, protect the minimal civil works requirement explicitly in the contract documents.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm the direction and tension of every belt under no load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check lubrication levels, grease lines and oil cooler operation.
- Measure noise and dust at the operator position against the local limit.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
The commissioning record becomes the reference for every liner change in the five-year plan.