Overview
Practical notes for bringing a HAMAC crushing or grinding plant into Mongolia, from quotation to commissioning.

Shipping & port
- Destination: Tianjin.
- FOB / CFR / CIF options.
- Container loading plan supplied.
Power & standards
- Voltage / frequency: 380V 50Hz.
- Standards: MNS.
- Motors set to local supply.
Documentation
HAMAC provides the certificates and packing list required for Mongolia customs clearance.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Tianjin |
| Site supply | 380V 50Hz |
| Local standards | MNS |
| Region | Asia |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | seven-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Specify motors, starters and documentation for 380V 50Hz and MNS before manufacture.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Local service partner, technician travel time and visa requirements for Mongolia.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Dust and noise control designed to the local emission limits for Mongolia.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
For high-tonnage aggregate supply, give the simple operator maintenance line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to Mongolia is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying simple operator maintenance on price alone and losing it in availability.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a greenfield site.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Comparing quotations with different port terms and calling the lower number cheaper.
On a greenfield site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Hand over the spare-parts list, manuals and maintenance schedule.
- Test emergency stops, pull wires and interlock trips in sequence.
- Calibrate the belt scale and any level probes against a known load.
- Sample each product fraction and compare with the specification.
- Measure and log the as-new CSS / setting for future wear comparison.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record the baseline grading curve for each product fraction.
- Measure noise and dust at the operator position against the local limit.
Keep the signed record; it is the only defensible baseline for later performance disputes.