Overview
HAMAC supplies crushing and grinding equipment to Vietnam, shipped to Ho Chi Minh and quoted to local standards (TCVN). Power is configured for 380V 50Hz.

Crushing equipment for Vietnam
- Popular material: Limestone, Granite.
- Destination port: Ho Chi Minh.
- Voltage / frequency: 380V 50Hz.
- Standards: TCVN.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 380V 50Hz and TCVN.
- FOB / CFR / CIF quotation to Ho Chi Minh.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Vietnam, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Ho Chi Minh |
| Site supply | 380V 50Hz |
| Local standards | TCVN |
| Region | Asia |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | seven-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and seven-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | minimal civil works |
| Evaluation horizon | seven-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Confirm the haul-road and stockpile plan with a coastal export terminal in mind before fixing conveyor lengths.
- Book container or flat-rack space to Ho Chi Minh and prepare the customs document set in advance.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Specify motors, starters and documentation for 380V 50Hz and TCVN before manufacture.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Nameplate data for 380V 50Hz and the TCVN certificate set.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Control system language, telemetry and remote diagnostics availability.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Guaranteed power draw and the minimal civil works trade-off it implies.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A seven-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Buying minimal civil works on price alone and losing it in availability.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Measure and log the as-new CSS / setting for future wear comparison.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Confirm the direction and tension of every belt under no load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Confirm all guards, emergency stops and pull-wire switches function.
The commissioning record becomes the reference for every liner change in the seven-year plan.