Overview
HAMAC supplies crushing and grinding equipment to Kenya, shipped to Mombasa and quoted to local standards (KS). Power is configured for 415V 50Hz.

Crushing equipment for Kenya
- Popular material: Limestone, Basalt.
- Destination port: Mombasa.
- Voltage / frequency: 415V 50Hz.
- Standards: KS.
What HAMAC provides
- Plant design for limestone and your capacity.
- Equipment configured to 415V 50Hz and KS.
- FOB / CFR / CIF quotation to Mombasa.
- Installation supervision, training and spare parts.
Logistics & documentation
HAMAC handles packing, container loading plan and the documentation required for Kenya, including certificates applicable to your market.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Mombasa |
| Site supply | 415V 50Hz |
| Local standards | KS |
| Region | Africa |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | ten-year view |
Use the table as a checklist when comparing quotations for the crushing and screening plant — a lower price often means one of these parameters was quietly reduced.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | tight grading compliance |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Nameplate data for 415V 50Hz and the KS certificate set.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Energy draw in kW and the expected kWh per tonne at the design duty.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
On demolition and recycling duties, the tight grading compliance objective changes which line deserves the most attention during value engineering.
Mistakes that cost more than the machine
- Buying tight grading compliance on price alone and losing it in availability.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Measure and log the as-new CSS / setting for future wear comparison.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Confirm the direction and tension of every belt under no load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Measure noise and dust at the operator position against the local limit.
- Check belt tracking, chute build-up and transfer-point dust.
- Calibrate the belt scale and any level probes against a known load.
- Hand over the spare-parts list, manuals and maintenance schedule.
The commissioning record becomes the reference for every liner change in the ten-year plan.