Overview
This page brings together the published PF Impact Crusher model data and the practical details of importing it into Venezuela — power supply, standards, shipping and commissioning. Popular feed materials in the market include Aggregates, Iron ore.

Published PF Impact Crusher data
| Published parameter | Nominal value |
|---|---|
| PF-1007 | Φ1000×700 mm 400×730 mm |
| PF-1010 | Φ1000×1050 mm 400×1080 mm |
| PF-1210 | Φ1250×1050 mm 400×1080 mm |
| PF-1214 | Φ1250×1400 mm 400×1430 mm |
| PF-1315 | Φ1320×1500 mm 860×1520 mm |
| PF-1520 | Φ1500×2000 mm 830×2040 mm |
Local conditions in Venezuela
- Destination port: Puerto Cabello.
- Site supply: 380V 60Hz.
- Standards: COVENIN.
- Common materials: Aggregates, Iron ore.
- Region: South America.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Puerto Cabello, sets motors and starters to 380V 60Hz, and supplies the certificate set applicable to COVENIN. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Puerto Cabello |
| Site supply | 380V 60Hz |
| Local standards | COVENIN |
| Region | South America |
| Machine line | PF Impact Crusher |
| Category | Impact Crusher |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
These values are the starting point for a written proposal on pf impact crusher; they are nominal and should be confirmed against a sample test before manufacture.
Published PF Impact Crusher model data
| Model | Rotor size | Feed opening | Max. Feeding size | Capacity | Motor Power | Weight | Overall dimension |
|---|---|---|---|---|---|---|---|
| PF-1007 | Φ1000×700 mm | 400×730 mm | 300 mm | 30-70 t/h | 37-45 kW | 12 t | 2330×1660×2300 mm |
| PF-1010 | Φ1000×1050 mm | 400×1080 mm | 350 mm | 50-90 t/h | 45-55 kW | 15 t | 2370×1700×2390 mm |
| PF-1210 | Φ1250×1050 mm | 400×1080 mm | 350 mm | 70-130 t/h | 110 kW | 17.7 t | 2680×2160×2800 mm |
| PF-1214 | Φ1250×1400 mm | 400×1430 mm | 350 mm | 100-180 t/h | 132 kW | 22.4 t | 2650×2460×2800 mm |
| PF-1315 | Φ1320×1500 mm | 860×1520 mm | 500 mm | 130-250 t/h | 220 kW | 27 t | 3180×2720×2620 mm |
| PF-1520 | Φ1500×2000 mm | 830×2040 mm | 700 mm | 300-550 t/h | 315-400 kW | 50.6 t | 3959×3564×3330 mm |
| PF-1620 | Φ1600×2000 mm | 2000×1600 mm | 500 mm | 400-700 t/h | 400-500 kW | 58 t | 4259×3660×3450 mm |
| PF-1820 | Φ1800×2000 mm | 1260×2040 mm | 800 mm | 600-800 t/h | 630-710 kW | 83.21 t | 4400×3866×4009 mm |
The impact crusher (impact crusher) is a new generation of impact crusher developed in combination with the specific working conditions of the sand and gravel. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for an existing quarry bench in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | an existing quarry bench |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for pf impact crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Confirm the haul-road and stockpile plan with an existing quarry bench in mind before fixing conveyor lengths.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
A realistic programme reserves time for permits, foundation curing and shipping to Venezuela before any steel is cut.

What to verify before you sign
- Wear-part interchangeability across machines in the same circuit.
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Liner alloy: high-chrome iron matched to the rock, not to the lowest purchase price.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Closed-side setting range and whether automatic setting regulation is included.
Score each supplier against the same ten items and keep the score sheet with the purchase file for the ten-year review.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A ten-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Confirm all guards, emergency stops and pull-wire switches function.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Verify rotation direction on every motor before coupling.
- Dry-run the plant empty for the specified period and record vibration.
- Confirm the direction and tension of every belt under no load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Calibrate the belt scale and any level probes against a known load.
Keep the signed record; it is the only defensible baseline for later performance disputes.