Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into United States — power supply, standards, shipping and commissioning. Popular feed materials in the market include Granite, Basalt, Limestone.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in United States
- Destination port: Los Angeles / Houston.
- Site supply: 460V 60Hz.
- Standards: ASTM / OSHA.
- Common materials: Granite, Basalt, Limestone.
- Region: North America.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Los Angeles / Houston, sets motors and starters to 460V 60Hz, and supplies the certificate set applicable to ASTM / OSHA. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Los Angeles / Houston |
| Site supply | 460V 60Hz |
| Local standards | ASTM / OSHA |
| Region | North America |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | continuous quarry production |
| Evaluation horizon | ten-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against continuous quarry production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a coastal export terminal in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | simple operator maintenance |
| Evaluation horizon | ten-year view |
| Site condition | a coastal export terminal |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Book container or flat-rack space to Los Angeles / Houston and prepare the customs document set in advance.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Availability of a rotating shift crew for liner changes and the lifting equipment on site.
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Dust and noise control designed to the local emission limits for United States.
- Whether the quoted t/h is achieved at continuous quarry production or under ideal laboratory feed.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Nameplate data for 460V 60Hz and the ASTM / OSHA certificate set.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- After-sales response time, technician availability and the warranty exclusions in writing.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
For mobile jaw crusher plant at your target tonnage, wear parts and energy usually outweigh the difference between two purchase prices within three to five years.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Buying simple operator maintenance on price alone and losing it in availability.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Overlooking dust, noise and water permits in United States until erection has already started.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Using one liner profile for both secondary and tertiary stages.
On a coastal export terminal, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Dry-run the plant empty for the specified period and record vibration.
- Confirm all guards, emergency stops and pull-wire switches function.
- Calibrate the belt scale and any level probes against a known load.
- Record power draw, tonnage and chamber pressure at steady state.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Sample each product fraction and compare with the specification.
The commissioning record becomes the reference for every liner change in the ten-year plan.