Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Philippines — power supply, standards, shipping and commissioning. Popular feed materials in the market include Limestone, Andesite.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Philippines
- Destination port: Manila.
- Site supply: 380V 60Hz.
- Standards: PNS.
- Common materials: Limestone, Andesite.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Manila, sets motors and starters to 380V 60Hz, and supplies the certificate set applicable to PNS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Manila |
| Site supply | 380V 60Hz |
| Local standards | PNS |
| Region | Asia |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | five-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a greenfield site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | five-year view |
| Site condition | a greenfield site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Philippines.

What to verify before you sign
- Product sampling points and the lab equipment needed for routine grading checks.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Decommissioning or relocation value at the end of a five-year horizon.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
For contract crushing on short-term sites, give the lowest energy per tonne line extra weight; a generic checklist will not rank the offers correctly.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Overlooking dust, noise and water permits in Philippines until erection has already started.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Measure and log the as-new CSS / setting for future wear comparison.
- Record the baseline grading curve for each product fraction.
- Check lubrication levels, grease lines and oil cooler operation.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Dry-run the plant empty for the specified period and record vibration.
- Confirm all guards, emergency stops and pull-wire switches function.
- Sample each product fraction and compare with the specification.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
The commissioning record becomes the reference for every liner change in the five-year plan.