Overview
This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Indonesia — power supply, standards, shipping and commissioning. Popular feed materials in the market include Coal, Limestone, Nickel.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Indonesia
- Destination port: Tanjung Priok.
- Site supply: 380V 50Hz.
- Standards: SNI.
- Common materials: Coal, Limestone, Nickel.
- Region: Asia.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Tanjung Priok, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to SNI. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Tanjung Priok |
| Site supply | 380V 50Hz |
| Local standards | SNI |
| Region | Asia |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | contract crushing on short-term sites |
| Evaluation horizon | five-year view |
These values are the starting point for a written proposal on mobile jaw crusher plant; they are nominal and should be confirmed against a sample test before manufacture.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against contract crushing on short-term sites: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | contract crushing on short-term sites |
| Primary objective | strict product cubicity |
| Evaluation horizon | five-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Book container or flat-rack space to Tanjung Priok and prepare the customs document set in advance.
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
For a rotating shift crew, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Whether the quoted t/h is achieved at contract crushing on short-term sites or under ideal laboratory feed.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Local service partner, technician travel time and visa requirements for Indonesia.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Dust and noise control designed to the local emission limits for Indonesia.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Letting the contract crushing on short-term sites duty be defined verbally instead of in the contract.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Buying strict product cubicity on price alone and losing it in availability.
- Overlooking dust, noise and water permits in Indonesia until erection has already started.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
Review the list with a rotating shift crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Check belt tracking, chute build-up and transfer-point dust.
- Check lubrication levels, grease lines and oil cooler operation.
- Measure noise and dust at the operator position against the local limit.
- Sample each product fraction and compare with the specification.
- Measure and log the as-new CSS / setting for future wear comparison.
- Confirm all guards, emergency stops and pull-wire switches function.
- Confirm the direction and tension of every belt under no load.
Keep the signed record; it is the only defensible baseline for later performance disputes.