Overview
This page brings together the published MTW European Type Grinding Mill model data and the practical details of importing it into Bolivia — power supply, standards, shipping and commissioning. Popular feed materials in the market include Gold ore, Tin.

Published MTW European Type Grinding Mill data
| Published parameter | Nominal value |
|---|---|
| Quantity of roller (PCS) | 4 4 |
| Inner diameter of ring (mm) | 1100 1380 |
| Rotary speed of main frame (r/min) | 120 96 |
| Max. Feeding size (mm) | < 30 < 35 |
| Output size (mm) | 1.6~0.045 1.6~0.045 |
| Output fineness | 0.038 0.038 |
Local conditions in Bolivia
- Destination port: Arica.
- Site supply: 380V 50Hz.
- Standards: NB.
- Common materials: Gold ore, Tin.
- Region: South America.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Arica, sets motors and starters to 380V 50Hz, and supplies the certificate set applicable to NB. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Arica |
| Site supply | 380V 50Hz |
| Local standards | NB |
| Region | South America |
| Machine line | MTW European Type Grinding Mill |
| Category | Grinding Mills |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | ten-year view |
The figures above are transcribed from published HAMAC data and from the material properties of the feed; site measurements take precedence.
Published MTW European Type Grinding Mill model data
| Item | MTW110 | MTW138 | MTW175 | MTW215 |
|---|---|---|---|---|
| Quantity of roller (PCS) | 4 | 4 | 5 | 5 |
| Inner diameter of ring (mm) | 1100 | 1380 | 1750 | 2150 |
| Rotary speed of main frame (r/min) | 120 | 96 | 75 | 65 |
| Max. Feeding size (mm) | < 30 | < 35 | < 40 | < 50 |
| Output size (mm) | 1.6~0.045 | 1.6~0.045 | 1.6~0.045 | 1.6-0.055 |
| Output fineness | 0.038 | 0.038 | 0.038 | 0.045 |
| Capacity (t/h) | 3.5~10 | 6.5~15 | 11~25 | 20-50 |
| Total weight (t) | 18 | 28.5 | 46 | 96 |
MTW European Tech. grinding mill (Raymond mill) is a national patented product developed by our company on the basis of absorbing European grinding technology and concepts. Read the table column by column against mine pre-beneficiation feed: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a remote mine site in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | tight grading compliance |
| Evaluation horizon | ten-year view |
| Site condition | a remote mine site |
| Operating team | a rotating shift crew |
Change any one of these assumptions and the recommended configuration for mtw european type grinding mill may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Plan training for a rotating shift crew on CSS adjustment, liner change-out and lock-out / tag-out.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Specify motors, starters and documentation for 380V 50Hz and NB before manufacture.
- Confirm the haul-road and stockpile plan with a remote mine site in mind before fixing conveyor lengths.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
Shortening this sequence is possible on a remote mine site, but only where the feed and product specification are already fully defined.

What to verify before you sign
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Whether the quoted t/h is achieved at mine pre-beneficiation feed or under ideal laboratory feed.
- Control system language, telemetry and remote diagnostics availability.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Wear-part interchangeability across machines in the same circuit.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Treat the percentages as a budgeting shape, not a quotation: HAMAC prices the equipment list in writing once the flow sheet is fixed.
Mistakes that cost more than the machine
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Using one liner profile for both secondary and tertiary stages.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Letting the mine pre-beneficiation feed duty be defined verbally instead of in the contract.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a remote mine site.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Confirm the direction and tension of every belt under no load.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Check belt tracking, chute build-up and transfer-point dust.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Sample each product fraction and compare with the specification.
- Record the baseline grading curve for each product fraction.
- Record power draw, tonnage and chamber pressure at steady state.
The commissioning record becomes the reference for every liner change in the ten-year plan.