Overview
This page brings together the published PE Series Jaw Crusher model data and the practical details of importing it into Australia — power supply, standards, shipping and commissioning. Popular feed materials in the market include Iron ore, Basalt, Coal.

Published PE Series Jaw Crusher data
| Published parameter | Nominal value |
|---|---|
| PEX250x750 | 250x750 mm 210 mm |
| PEX250x1000 | 250x1000 mm 210 mm |
| PEX250x1200 | 250x1200 mm 210 mm |
| PEX300x1300 | 300x1300 mm 250 mm |
| PE400×600 | 400×600 mm 340 mm |
| PE500×750 | 500×750 mm 425 mm |
Local conditions in Australia
- Destination port: Sydney.
- Site supply: 415V 50Hz.
- Standards: AS.
- Common materials: Iron ore, Basalt, Coal.
- Region: Oceania.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Sydney, sets motors and starters to 415V 50Hz, and supplies the certificate set applicable to AS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Sydney |
| Site supply | 415V 50Hz |
| Local standards | AS |
| Region | Oceania |
| Machine line | PE Series Jaw Crusher |
| Category | Jaw Crusher |
| Assumed duty | continuous quarry production |
| Evaluation horizon | seven-year view |
Ask for the same table from any competing supplier; without it, an offer for pe series jaw crusher cannot be compared on scope.
Published PE Series Jaw Crusher model data
| Model | Input Size | Max Feeding Size | Output Range | Capacity | Engine Power | Weight |
|---|---|---|---|---|---|---|
| PEX250x750 | 250x750 mm | 210 mm | 25-60 mm | 13-35 T/H | 30 KW | 5.5 T |
| PEX250x1000 | 250x1000 mm | 210 mm | 25-60 mm | 16-52 T/H | 37 KW | 7 T |
| PEX250x1200 | 250x1200 mm | 210 mm | 25-60 mm | 20-61 T/H | 55 KW | 9.5 T |
| PEX300x1300 | 300x1300 mm | 250 mm | 20-90 mm | 16-105 T/H | 75 KW | 15.6 T |
| PE400×600 | 400×600 mm | 340 mm | 40-100 mm | 16-60 T/H | 30 KW | 6.7 T |
| PE500×750 | 500×750 mm | 425 mm | 50-100 mm | 40-110 T/H | 55 KW | 11.7 T |
| PE600×900 | 600×900 mm | 500 mm | 65-180 mm | 80-180 T/H | 55-75 KW | 16.1 T |
| PE750×1060 | 750×1060 mm | 630 mm | 80-180 mm | 110-320 T/H | 90-110 KW | 30.1 T |
Jaw crushers are often used for primary crushing in mine material crushing. Read the table column by column against continuous quarry production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a confined urban yard in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | lowest energy per tonne |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for pe series jaw crusher may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Australia.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- Product sampling points and the lab equipment needed for routine grading checks.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Choke-feed arrangement: surge bin, feeder control and level indication.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
Share this list with an owner-operator team as well as procurement; operators are the ones who live with the omissions.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
The weighting shifts with hardness and scale — a hard feed pushes the wear line up, while a larger plant pushes equipment share up.
Mistakes that cost more than the machine
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Using one liner profile for both secondary and tertiary stages.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Measure and log the as-new CSS / setting for future wear comparison.
- Check belt tracking, chute build-up and transfer-point dust.
- Record power draw, tonnage and chamber pressure at steady state.
- Record the baseline grading curve for each product fraction.
- Verify rotation direction on every motor before coupling.
- Calibrate the belt scale and any level probes against a known load.
- Check lubrication levels, grease lines and oil cooler operation.
The commissioning record becomes the reference for every liner change in the seven-year plan.