This page brings together the published Mobile Jaw Crusher Plant model data and the practical details of importing it into Australia — power supply, standards, shipping and commissioning. Popular feed materials in the market include Iron ore, Basalt, Coal.

Published Mobile Jaw Crusher Plant data
| Published parameter | Nominal value |
|---|---|
| MJ69 | 95-165 mm 30-85 m³/h |
| MJC96 | 60-175 mm 60-200 m³/h |
| MJ750 | 80-180 mm 72-150 m³/h |
| MJC106 | 70-200 mm 100-300 m³/h |
Local conditions in Australia
- Destination port: Sydney.
- Site supply: 415V 50Hz.
- Standards: AS.
- Common materials: Iron ore, Basalt, Coal.
- Region: Oceania.
Delivery scope
HAMAC quotes FOB, CFR or CIF to Sydney, sets motors and starters to 415V 50Hz, and supplies the certificate set applicable to AS. Workshop assembly, test, container loading plan and installation supervision are included in a turnkey scope.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Sydney |
| Site supply | 415V 50Hz |
| Local standards | AS |
| Region | Oceania |
| Machine line | Mobile Jaw Crusher Plant |
| Category | Wheel Type Mobile Crushers |
| Assumed duty | continuous quarry production |
| Evaluation horizon | seven-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and seven-year operating plan.
Published Mobile Jaw Crusher Plant model data
| Model | Discharge Adjustment | Nominal Capacity | Dimension | Magnetic Separator | Axles |
|---|---|---|---|---|---|
| MJ69 | 95-165 mm | 30-85 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJC96 | 60-175 mm | 60-200 m³/h | 11097×3759×3500 mm | RCYD800 | Double |
| MJ750 | 80-180 mm | 72-150 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
| MJC106 | 70-200 mm | 100-300 m³/h | 13300×2900×4440 mm | RCYD1000 | Three |
The tire-type mobilejaw crusher mobile is a mobile primary crushing equipment composed of vibratingfeeder, jaw crusher, conveyor belt and other components. Read the table column by column against continuous quarry production: the model you pick is the one whose published range brackets your target tonnage, not simply the largest machine in the series. Availability, motor rating and shipping data are re-confirmed for a brownfield extension in the written HAMAC proposal.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | maximum mechanical availability |
| Evaluation horizon | seven-year view |
| Site condition | a brownfield extension |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for mobile jaw crusher plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Confirm the haul-road and stockpile plan with a brownfield extension in mind before fixing conveyor lengths.
- Book container or flat-rack space to Sydney and prepare the customs document set in advance.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Review the crusher chamber profile with the liner supplier against the feed material.
Most delays at this stage come from missing feed data rather than from manufacturing capacity.

What to verify before you sign
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Availability of an owner-operator team for liner changes and the lifting equipment on site.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
Ask each supplier to price the same list. Quotations for mobile jaw crusher plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Using one liner profile for both secondary and tertiary stages.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Overlooking dust, noise and water permits in Australia until erection has already started.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
On a brownfield extension, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Sample each product fraction and compare with the specification.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Record the baseline grading curve for each product fraction.
- Measure noise and dust at the operator position against the local limit.
- Check belt tracking, chute build-up and transfer-point dust.
- Hand over the spare-parts list, manuals and maintenance schedule.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Dry-run the plant empty for the specified period and record vibration.
Keep the signed record; it is the only defensible baseline for later performance disputes.