Overview
Two-stage crushing then raw grinding to kiln feed. In Russia the most frequently processed feed materials are Granite, Coal, Basalt, and equipment is normally delivered through St Petersburg on 380V 50Hz supplies.

Materials in scope
- Limestone — Mohs 3, ~100 MPa, low abrasion
- Gypsum — Mohs 1.5, ~30 MPa, low abrasion
- Bauxite — Mohs 2, ~50 MPa, low abrasion
Recommended machines
- PE Series Jaw Crusher
- PF Impact Crusher
- Mobile Impact Crusher Plant
- Vibrating Feeder
- Vibrating Screen
Engineering for Russia
| Item | Reference |
|---|---|
| Port | St Petersburg |
| Power | 380V 50Hz |
| Standards | GOST |
| Region | Europe/Asia |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | St Petersburg |
| Site supply | 380V 50Hz |
| Local standards | GOST |
| Region | Europe/Asia |
| Application | Cement & Raw Meal |
| Typical feed | Limestone, Gypsum, Bauxite |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | seven-year view |
Ask for the same table from any competing supplier; without it, an offer for the crushing and screening plant cannot be compared on scope.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | strict product cubicity |
| Evaluation horizon | seven-year view |
| Site condition | a remote mine site |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Book container or flat-rack space to St Petersburg and prepare the customs document set in advance.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Specify motors, starters and documentation for 380V 50Hz and GOST before manufacture.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
On high-tonnage aggregate supply, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Product sampling points and the lab equipment needed for routine grading checks.
- Guaranteed power draw and the strict product cubicity trade-off it implies.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Using one liner profile for both secondary and tertiary stages.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Overlooking dust, noise and water permits in Russia until erection has already started.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
On a remote mine site, the civil and logistics items deserve as much attention as the crusher itself.
Commissioning checklist
- Hand over the spare-parts list, manuals and maintenance schedule.
- Confirm all guards, emergency stops and pull-wire switches function.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Record the baseline grading curve for each product fraction.
- Check lubrication levels, grease lines and oil cooler operation.
- Sample each product fraction and compare with the specification.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
Keep the signed record; it is the only defensible baseline for later performance disputes.