Overview
Single-size, high-PSV, low-flakiness aggregate. In Egypt the most frequently processed feed materials are Limestone, Granite, and equipment is normally delivered through Alexandria on 380V 50Hz supplies.

Materials in scope
- Basalt — Mohs 6, ~200 MPa, high abrasion
- Granite — Mohs 6.5, ~180 MPa, high abrasion
- Andesite — Mohs 6, ~170 MPa, high abrasion
Recommended machines
- PE Series Jaw Crusher
- HPT Multi-Cylinder Hydraulic Cone Crusher
- VSI Vertical Shaft Impact Crusher (Sand Making Machine)
Engineering for Egypt
| Item | Reference |
|---|---|
| Port | Alexandria |
| Power | 380V 50Hz |
| Standards | EOS |
| Region | Africa |
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Destination port | Alexandria |
| Site supply | 380V 50Hz |
| Local standards | EOS |
| Region | Africa |
| Application | Road & Railway Ballast |
| Typical feed | Basalt, Granite, Andesite |
| Assumed duty | high-tonnage aggregate supply |
| Evaluation horizon | seven-year view |
Treat this as a living sheet. Every revision of the flow sheet for Egypt should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | high-tonnage aggregate supply |
| Primary objective | tight grading compliance |
| Evaluation horizon | seven-year view |
| Site condition | a brownfield extension |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Size the primary stage for your target tonnage with a 10–20% surge allowance — never on nameplate throughput alone.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
For a mixed local and expatriate team, the commissioning and training steps need more calendar time than the mechanical erection itself.

What to verify before you sign
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Closed-side setting range and whether automatic setting regulation is included.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Dust and noise control designed to the local emission limits for Egypt.
- Liner alloy: Mn22 matched to the rock, not to the lowest purchase price.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 53% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 14% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A seven-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Letting the high-tonnage aggregate supply duty be defined verbally instead of in the contract.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Assuming the manufacturer's warranty covers wear parts and consumables.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Test emergency stops, pull wires and interlock trips in sequence.
- Check lubrication levels, grease lines and oil cooler operation.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Dry-run the plant empty for the specified period and record vibration.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm the direction and tension of every belt under no load.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Calibrate the belt scale and any level probes against a known load.
Keep the signed record; it is the only defensible baseline for later performance disputes.