Overview
A under 50 tph crushing plant is a common size for United States. Main machines: small jaw + impact/cone, skid or mobile. Contractor and pilot scale, fast set-up.

Main equipment
- small jaw + impact/cone, skid or mobile
- Shipped to Los Angeles / Houston.
- Configured to 460V 60Hz / ASTM / OSHA.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For United States
- Port: Los Angeles / Houston.
- Voltage: 460V 60Hz.
- Standards: ASTM / OSHA.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 10–50 t/h |
| Typical main line | small jaw + impact/cone, skid or mobile |
| Scale note | Contractor and pilot scale, fast set-up. |
| Destination port | Los Angeles / Houston |
| Site supply | 460V 60Hz |
| Local standards | ASTM / OSHA |
| Region | North America |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | single-project view |
At manufactured-sand production, the ranking of these parameters changes: minimal civil works usually becomes the deciding constraint rather than the headline tonnage.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | minimal civil works |
| Evaluation horizon | single-project view |
| Site condition | a confined urban yard |
| Operating team | an owner-operator team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for 10–50 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Book container or flat-rack space to Los Angeles / Houston and prepare the customs document set in advance.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Verify the electrical single-line diagram, cable sizing and starter type with the local utility.
- Plan training for an owner-operator team on CSS adjustment, liner change-out and lock-out / tag-out.
- Review the crusher chamber profile with the liner supplier against the feed material.
The sequence is deliberately front-loaded — decisions taken before manufacture are cheap, changes made on site are not.

What to verify before you sign
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Liner alloy: Mn13 matched to the rock, not to the lowest purchase price.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 10–50 t/h.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- After-sales response time, technician availability and the warranty exclusions in writing.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 49% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 8% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
A single-project view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Buying minimal civil works on price alone and losing it in availability.
- Comparing quotations with different port terms and calling the lower number cheaper.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Letting the manufactured-sand production duty be defined verbally instead of in the contract.
- Omitting a bypass chute, so a single screen fault stops the whole line.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
Review the list with an owner-operator team before the order is placed — they will recognise most of them.
Commissioning checklist
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Verify rotation direction on every motor before coupling.
- Measure noise and dust at the operator position against the local limit.
- Check lubrication levels, grease lines and oil cooler operation.
- Confirm all guards, emergency stops and pull-wire switches function.
- Dry-run the plant empty for the specified period and record vibration.
- Test emergency stops, pull wires and interlock trips in sequence.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
The commissioning record becomes the reference for every liner change in the single-project plan.