Overview
A 200–300 tph crushing plant is a common size for Mexico. Main machines: large jaw + 2× cone + screens. Mid-size quarry, multiple products.

Main equipment
- large jaw + 2× cone + screens
- Shipped to Manzanillo.
- Configured to 460V 60Hz / NOM.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Mexico
- Port: Manzanillo.
- Voltage: 460V 60Hz.
- Standards: NOM.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 200–300 t/h |
| Typical main line | large jaw + 2× cone + screens |
| Scale note | Mid-size quarry, multiple products. |
| Destination port | Manzanillo |
| Site supply | 460V 60Hz |
| Local standards | NOM |
| Region | North America |
| Assumed duty | demolition and recycling duties |
| Evaluation horizon | seven-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and seven-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | demolition and recycling duties |
| Primary objective | simple operator maintenance |
| Evaluation horizon | seven-year view |
| Site condition | a confined urban yard |
| Operating team | a mixed local and expatriate team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Plan training for a mixed local and expatriate team on CSS adjustment, liner change-out and lock-out / tag-out.
- Commission with graded load, sample the product grading, then train operators on liner change-out and daily checks.
- Confirm the haul-road and stockpile plan with a confined urban yard in mind before fixing conveyor lengths.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Specify motors, starters and documentation for 460V 60Hz and NOM before manufacture.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
Each step has an owner and a document: flow sheet, general arrangement, foundation reference, packing list and acceptance protocol.

What to verify before you sign
- Guaranteed power draw and the simple operator maintenance trade-off it implies.
- Dust and noise control designed to the local emission limits for Mexico.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Product sampling points and the lab equipment needed for routine grading checks.
- Liner alloy: Mn18 matched to the rock, not to the lowest purchase price.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for 200–300 t/h.
- Decommissioning or relocation value at the end of a seven-year horizon.
- Nameplate data for 460V 60Hz and the NOM certificate set.
The cheapest offer usually wins on equipment and loses on one of the last six items — freight terms, spares or the acceptance test.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 11% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
A seven-year view normally reverses the ranking of two otherwise similar offers once wear and energy are included.
Mistakes that cost more than the machine
- Comparing quotations with different port terms and calling the lower number cheaper.
- Overlooking dust, noise and water permits in Mexico until erection has already started.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Buying simple operator maintenance on price alone and losing it in availability.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 200–300 t/h.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Using one liner profile for both secondary and tertiary stages.
- Forgetting surge capacity — an intermittent loader starves the chamber and ruins particle shape.
For demolition and recycling duties, protect the simple operator maintenance requirement explicitly in the contract documents.
Commissioning checklist
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Measure noise and dust at the operator position against the local limit.
- Confirm the direction and tension of every belt under no load.
- Check belt tracking, chute build-up and transfer-point dust.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Dry-run the plant empty for the specified period and record vibration.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
For a mixed local and expatriate team, run through this list twice — once with the supervisor and once without.