Overview
A 50–100 tph crushing plant is a common size for Tunisia. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Main equipment
- PE jaw + PF impact / cone + 2-deck screen
- Shipped to Tunis.
- Configured to 380V 50Hz / NT.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Tunisia
- Port: Tunis.
- Voltage: 380V 50Hz.
- Standards: NT.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Destination port | Tunis |
| Site supply | 380V 50Hz |
| Local standards | NT |
| Region | Africa |
| Assumed duty | manufactured-sand production |
| Evaluation horizon | three-year view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | manufactured-sand production |
| Primary objective | strict product cubicity |
| Evaluation horizon | three-year view |
| Site condition | a confined urban yard |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Book container or flat-rack space to Tunis and prepare the customs document set in advance.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Size the primary stage for 50–100 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Set the maintenance stock list from the expected wear rate, not from a percentage of the equipment price.
- Define the acceptance test: sampling points, test duration, moisture range and who signs the protocol.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Tunisia.

What to verify before you sign
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Ambient temperature, altitude and dust load derating for motors and hydraulics.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Product sampling points and the lab equipment needed for routine grading checks.
- Dust and noise control designed to the local emission limits for Tunisia.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to Tunisia is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Overlooking dust, noise and water permits in Tunisia until erection has already started.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Buying strict product cubicity on price alone and losing it in availability.
- Using one liner profile for both secondary and tertiary stages.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
Every item on this list has cost someone a commissioning date; none of them requires new technology to avoid.
Commissioning checklist
- Record power draw, tonnage and chamber pressure at steady state.
- Verify rotation direction on every motor before coupling.
- Measure and log the as-new CSS / setting for future wear comparison.
- Test emergency stops, pull wires and interlock trips in sequence.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Record the baseline grading curve for each product fraction.
- Agree the punch list, sign the hand-over protocol and file the as-built drawings.
- Hand over the spare-parts list, manuals and maintenance schedule.
The commissioning record becomes the reference for every liner change in the three-year plan.