Overview
A 50–100 tph crushing plant is a common size for Qatar. Main machines: PE jaw + PF impact / cone + 2-deck screen. Small quarries and concrete plants.

Main equipment
- PE jaw + PF impact / cone + 2-deck screen
- Shipped to Hamad.
- Configured to 415V 50Hz / QCS.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Qatar
- Port: Hamad.
- Voltage: 415V 50Hz.
- Standards: QCS.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 50–100 t/h |
| Typical main line | PE jaw + PF impact / cone + 2-deck screen |
| Scale note | Small quarries and concrete plants. |
| Destination port | Hamad |
| Site supply | 415V 50Hz |
| Local standards | QCS |
| Region | Middle East |
| Assumed duty | mine pre-beneficiation feed |
| Evaluation horizon | single-project view |
Treat this as a living sheet. Every revision of the flow sheet for Qatar should update the same fields so the equipment list stays traceable.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | mine pre-beneficiation feed |
| Primary objective | simple operator maintenance |
| Evaluation horizon | single-project view |
| Site condition | a remote mine site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Run a sieve analysis on a representative sample and attach the grading curve to the enquiry.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
- Budget for water, dust extraction and spillage handling as part of the plant, not as an afterthought.
- Book container or flat-rack space to Hamad and prepare the customs document set in advance.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Size the primary stage for 50–100 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
On mine pre-beneficiation feed, step ordering matters: survey and sampling must precede the equipment list, or the plant is sized to a guess.

What to verify before you sign
- Closed-side setting range and whether automatic setting regulation is included.
- Access for liner change-out — crane radius, lifting points and clearance around the chamber.
- Product sampling points and the lab equipment needed for routine grading checks.
- Control system language, telemetry and remote diagnostics availability.
- Maximum feed lump and gradation — a chamber that cannot accept the top size will bridge on day one.
- Decommissioning or relocation value at the end of a single-project horizon.
- Availability of a small contractor crew for liner changes and the lifting equipment on site.
- Screen deck count, aperture and area; ask for the efficiency calculation, not just the mesh size.
- Energy draw in kW and the expected kWh per tonne at the design duty.
The relative weight of each item changes with the project: wear parts dominate on abrasive rock, availability dominates on remote sites.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 50% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 9% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Include downtime in the model. An unplanned liner change on a remote site costs far more than the casting itself.
Mistakes that cost more than the machine
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Using one liner profile for both secondary and tertiary stages.
- Specifying motors for the wrong voltage or frequency and rewinding them on site.
- Assuming a mobile plant can match a stationary line on high-tonnage, multi-product duty.
- Assuming the manufacturer's warranty covers wear parts and consumables.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Undersizing the screen, then blaming the crusher for a plant that never reaches 50–100 t/h.
- Omitting a bypass chute, so a single screen fault stops the whole line.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Record the baseline grading curve for each product fraction.
- Test emergency stops, pull wires and interlock trips in sequence.
- Check belt tracking, chute build-up and transfer-point dust.
- Confirm the direction and tension of every belt under no load.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check hydraulic pressure, accumulator pre-charge and tramp-release function.
- Sample each product fraction and compare with the specification.
- Measure noise and dust at the operator position against the local limit.
Keep the signed record; it is the only defensible baseline for later performance disputes.