Overview
A 100–200 tph crushing plant is a common size for Ecuador. Main machines: PE/PEW jaw + cone + 3-deck screen. Most common export plant size.

Main equipment
- PE/PEW jaw + cone + 3-deck screen
- Shipped to Guayaquil.
- Configured to 380V 60Hz / NEC.
Selection
- Size to saleable t/h +10–20% surge.
- Hard rock → jaw+cone; soft → jaw+impact.
- Add VSI for sand/shape.
For Ecuador
- Port: Guayaquil.
- Voltage: 380V 60Hz.
- Standards: NEC.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Design capacity | 100–200 t/h |
| Typical main line | PE/PEW jaw + cone + 3-deck screen |
| Scale note | Most common export plant size. |
| Destination port | Guayaquil |
| Site supply | 380V 60Hz |
| Local standards | NEC |
| Region | South America |
| Assumed duty | cement raw-meal preparation |
| Evaluation horizon | ten-year view |
Where a value is shown as nominal, the written proposal states the guaranteed figure for your material, feed grading and ten-year operating plan.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | cement raw-meal preparation |
| Primary objective | lowest cost per tonne |
| Evaluation horizon | ten-year view |
| Site condition | a greenfield site |
| Operating team | a small contractor crew |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Size the primary stage for 100–200 t/h with a 10–20% surge allowance — never on nameplate throughput alone.
- Lay out the PE/PEW jaw + cone + 3-deck screen arrangement with straight conveyor runs and crane access for liner changes.
- Allocate screen area per deck; blinding and pegging are the most common hidden bottlenecks in a new plant.
- Review the crusher chamber profile with the liner supplier against the feed material.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Set the closed-side setting or rotor speed against the required product fractions, then verify the expected reduction ratio.
- Confirm the haul-road and stockpile plan with a greenfield site in mind before fixing conveyor lengths.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
- Check bearing and lubrication arrangements against the ambient temperature range at the site.
A HAMAC project manager stays with the order from the first data sheet through hand-over in Ecuador.

What to verify before you sign
- After-sales response time, technician availability and the warranty exclusions in writing.
- Tramp-iron protection — hydraulic release, magnet and metal detection on the feed belt.
- Delivery terms (FOB / CFR / CIF) with the destination port named explicitly.
- Closed-side setting range and whether automatic setting regulation is included.
- Whether the quoted t/h is achieved at cement raw-meal preparation or under ideal laboratory feed.
- Energy draw in kW and the expected kWh per tonne at the design duty.
- Decommissioning or relocation value at the end of a ten-year horizon.
- Spare motor, gearbox and hydraulic pump lead times from the nearest HAMAC stock point.
- Written performance guarantee, sampling method and acceptance-test protocol.
Bring this list to the design review — it is cheaper to resolve an omission on paper than during commissioning.
Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 51% | Model size, number of stages and automation level |
| Ocean freight & insurance | 12% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 7% | kWh per tonne, local tariff and dust suppression water |
Freight to Ecuador is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Selecting the cheapest liner alloy for hard, high-silica rock and paying for it in change-outs.
- Letting the cement raw-meal preparation duty be defined verbally instead of in the contract.
- Buying lowest cost per tonne on price alone and losing it in availability.
- Using one liner profile for both secondary and tertiary stages.
- Leaving tramp-iron protection out of the scope to save a small percentage of capital.
- Planning the crusher but not the conveyors, transfer chutes and stockpile capacity around it.
- Ignoring clay and moisture until the first wet season, when decks blind and chambers pack.
Review the list with a small contractor crew before the order is placed — they will recognise most of them.
Commissioning checklist
- Calibrate the belt scale and any level probes against a known load.
- Record power draw, tonnage and chamber pressure at steady state.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Check lubrication levels, grease lines and oil cooler operation.
- Sample each product fraction and compare with the specification.
- Test emergency stops, pull wires and interlock trips in sequence.
- Measure noise and dust at the operator position against the local limit.
- Confirm all guards, emergency stops and pull-wire switches function.
The commissioning record becomes the reference for every liner change in the ten-year plan.