Overview
Cost drivers for a construction & demolition recycling plant:

Cost factors
- Capacity & stages.
- Mobility.
- Wear-part grade.
- Automation & dust control.
Reference data for this configuration
| Parameter | Reference value |
|---|---|
| Application | Construction & Demolition Recycling |
| Typical feed | Construction waste, Concrete & asphalt |
| Assumed duty | continuous quarry production |
| Evaluation horizon | single-project view |
HAMAC engineers fill in the same fields on the project data sheet, which is why two plants of similar tonnage can still require different machines.
Project profile these notes assume
| Assumption | Value |
|---|---|
| Operating duty | continuous quarry production |
| Primary objective | minimal civil works |
| Evaluation horizon | single-project view |
| Site condition | a brownfield extension |
| Operating team | a full-time plant team |
Change any one of these assumptions and the recommended configuration for the crushing and screening plant may change. HAMAC re-runs the same checks against your own numbers once the enquiry data sheet is received.
From enquiry to the first saleable tonne
- Log tonnes per liner set and kWh per tonne from day one so you have a real cost baseline within a quarter.
- Choose compression or impact reduction according to hardness, silica content and required particle shape.
- Sequence delivery so foundations cure while the equipment is still in manufacture.
- Include dust suppression, guarding, emergency stops and lock-out points in the layout drawing.
- Confirm site voltage, frequency and applicable conformity standards before manufacture.
- Plan training for a full-time plant team on CSS adjustment, liner change-out and lock-out / tag-out.
- Survey the feed: the feed material; record top size, bulk density, moisture and clay content before fixing the flow sheet.
- Lay out conveyors, access ways, stockpile capacity and drainage before ordering steelwork.
- Record the as-built settings and give the operator a written daily, weekly and monthly schedule.
A realistic programme reserves time for permits, foundation curing and shipping to your market before any steel is cut.
What to verify before you sign
- Spare-parts consignment: one full liner or blow-bar set plus meshes, belts, bearings and seals.
- Liner alloy: Mn18 with ceramic inserts matched to the rock, not to the lowest purchase price.
- Wear-part interchangeability across machines in the same circuit.
- Whether the quoted t/h is achieved at continuous quarry production or under ideal laboratory feed.
- Control system language, telemetry and remote diagnostics availability.
- Availability of a full-time plant team for liner changes and the lifting equipment on site.
- Saleable tonnes per hour at each product size, not gross crusher throughput, for your target tonnage.
- Written performance guarantee, sampling method and acceptance-test protocol.
- Erection scope: supervision only, or full civil, mechanical and electrical installation.
Ask each supplier to price the same list. Quotations for the crushing and screening plant only become comparable when the scope is identical.

Where the money actually goes
| Cost line | Indicative share | What moves the number |
|---|---|---|
| Equipment & drive packages | 54% | Model size, number of stages and automation level |
| Ocean freight & insurance | 8% | Destination port, container count and out-of-gauge cargo |
| Civil works & foundations | 8% | Soil conditions, dynamic loads and site preparation |
| Erection, commissioning & training | 7% | Local labour, supervision scope and schedule |
| First-year wear parts | 15% | Rock abrasiveness, liner grade and operating hours |
| Power, lubricants & consumables | 8% | kWh per tonne, local tariff and dust suppression water |
Freight to your market is volatile; ask for the quotation to state validity and the port basis rather than a single delivered number.
Mistakes that cost more than the machine
- Skipping the acceptance test, so no one has a baseline to measure degradation against.
- Buying on nameplate t/h without converting to saleable product at the specified fractions.
- Letting the continuous quarry production duty be defined verbally instead of in the contract.
- Choosing screen apertures before the concrete or asphalt mix design is fixed.
- Undersizing the screen, then blaming the crusher for a plant that never reaches your target tonnage.
- Ordering no spares with the plant and waiting six weeks for the first liner set.
- Overlooking dust, noise and water permits in your market until erection has already started.
- Skipping a geotechnical check and discovering settlement under the primary crusher at a brownfield extension.
Review the list with a full-time plant team before the order is placed — they will recognise most of them.
Commissioning checklist
- Measure noise and dust at the operator position against the local limit.
- Verify chute liners, skirt rubber and impact bars after the first hour of feed.
- Introduce feed in graded steps: 25%, 50%, 75%, then full load.
- Test emergency stops, pull wires and interlock trips in sequence.
- Check lubrication levels, grease lines and oil cooler operation.
- Check belt tracking, chute build-up and transfer-point dust.
- Sample each product fraction and compare with the specification.
- Hand over the spare-parts list, manuals and maintenance schedule.
The commissioning record becomes the reference for every liner change in the single-project plan.