Design basis for river pebble arid desert site
The design basis starts with the rock, not the machine. River pebble is rated at 100–200 MPa compressive strength with very high abrasiveness, medium moisture sensitivity and a loose bulk density around 1.48 t/m³. Rounded, high-silica feed resists compression and wears blow bars quickly; rock-on-rock VSI is normally preferred for the shaping stage. Measurements are only comparable when the sieve standard is the same.
A arid desert site must control dust with very little water available, constrained by extreme heat, abrasive airborne dust and limited water. The commercial priority is dry dust extraction. For this combination HAMAC works from an indicative design point of 150 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of manufactured sand, 5–20 mm aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | River pebble · 100–200 MPa · abrasion very high |
| Design throughput | 150 t/h saleable product (150–350 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | manufactured sand, 5–20 mm aggregate |
| Loose bulk density | 1.48 t/m³ |
| Suggested circuit | jaw → cone → VSI → sand washer / classifier |

Why unplanned downtime appears in this circuit
Short stops accumulate into a large annual output loss. In a river pebble arid desert site this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- no planned change-out window for wear parts
- spares with long lead times are not held on site
- interlock and lubrication faults are cleared without root-cause logging
The reference conditions should be attached to every figure quoted. Before changing a crusher setting, check these in order: 1) report availability and utilisation separately each month; 2) review the top five stop causes; 3) verify spares stock against the recommended list. Confirm all figures in a written proposal before purchase.
Recommended equipment configuration
For river pebble at 150 t/h the working train is jaw → cone → VSI → sand washer / classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for river pebble and for a softer rock. Measurements are only comparable when the sieve standard is the same.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~188 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | cone |
| Screening | Multi-deck screen sized for 20% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.48 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 370 kW order-of-magnitude connected load |
The corrective actions for unplanned downtime are applied on top of this base circuit: schedule liner changes by measured wear rate, not by calendar; hold a recommended spares list for the first two years; log every stop with a fault code and a corrective action.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 20% and a screen efficiency target above 90%. The reference conditions should be attached to every figure quoted.
- Report availability and utilisation separately each month
- Review the top five stop causes
- Verify spares stock against the recommended list
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 150 t/h nominal |
| Grading | Full sieve analysis, agreed standard, manufactured sand, 5–20 mm aggregate |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 370 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Confirm all figures in a written proposal before purchase. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for river pebble, while dry dust extraction determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 20% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 150 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Measurements are only comparable when the sieve standard is the same. Confirm all figures in a written proposal before purchase. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.