Design basis for marble quarry expansion
The design basis starts with the rock, not the machine. Marble is rated at 50–120 MPa compressive strength with low abrasiveness, low moisture sensitivity and a loose bulk density around 1.40 t/m³. Valued for whiteness, so iron contamination and tramp metal protection matter more than reduction ratio. Indicative values are starting points for a design, not guarantees.
A quarry expansion must add saleable output without stopping the existing line, constrained by a shared feed point and limited stockpile area. The commercial priority is throughput continuity. For this combination HAMAC works from an indicative design point of 170 t/h of saleable product, with a maximum feed top size near 600 mm and target fractions of ground calcium carbonate, chips, aggregate.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Marble · 50–120 MPa · abrasion low |
| Design throughput | 170 t/h saleable product (150–300 t/h scenario band) |
| Maximum feed size | ~600 mm |
| Target product | ground calcium carbonate, chips, aggregate |
| Loose bulk density | 1.40 t/m³ |
| Suggested circuit | jaw → impact → screen → grinding / classifier |

Why tramp metal damage appears in this circuit
A bucket tooth or rebar reaches the chamber and damages liners. In a marble quarry expansion this is usually a system symptom rather than a single machine fault. Start from the product specification and work backwards to the feed.
- no magnet or detector ahead of the crusher
- hydraulic relief and tramp-release settings are untested
- demolition feed is not pre-sorted
Measurements are only comparable when the sieve standard is the same. Before changing a crusher setting, check these in order: 1) test the detector with a sample metal piece each week; 2) inspect the chamber after any release event; 3) log every tramp incident and its cause. A signed settings log at handover protects both parties later.
Recommended equipment configuration
For marble at 170 t/h the working train is jaw → impact → screen → grinding / classifier. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for marble and for a softer rock. Indicative values are starting points for a design, not guarantees.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~213 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~26 mm at the secondary stage |
| Secondary / tertiary | impact |
| Screening | Multi-deck screen sized for 40% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.40 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 540 kW order-of-magnitude connected load |
The corrective actions for tramp metal damage are applied on top of this base circuit: fit a magnetic separator and a belt metal detector; test hydraulic release under no-load conditions; add a picking station for reinforced concrete feed.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 26 mm, a circulating load around 40% and a screen efficiency target above 90%. Measurements are only comparable when the sieve standard is the same.
- Test the detector with a sample metal piece each week
- Inspect the chamber after any release event
- Log every tramp incident and its cause
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 170 t/h nominal |
| Grading | Full sieve analysis, agreed standard, ground calcium carbonate, chips, aggregate |
| Crusher setting | CSS measured and logged, ~26 mm starting point |
| Power | Main-drive current at steady feed, 540 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
A signed settings log at handover protects both parties later. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for marble, while throughput continuity determines how much lost production actually costs. Start from the product specification and work backwards to the feed.
- Ask every supplier for the same flow sheet and mass balance, including the 40% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 170 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
Indicative values are starting points for a design, not guarantees. A signed settings log at handover protects both parties later. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.
