Design basis for limestone high-altitude site
The design basis starts with the rock, not the machine. Limestone is rated at 30–150 MPa compressive strength with low abrasiveness, low–medium moisture sensitivity and a loose bulk density around 1.35 t/m³. Soft and non-abrasive enough for impact crushing in a single stage; clay seams and moisture are the usual complications. The reference conditions should be attached to every figure quoted.
A high-altitude site must derate motors and cooling for thin air, constrained by reduced air density and large day/night temperature swings. The commercial priority is drive and cooling margins. For this combination HAMAC works from an indicative design point of 110 t/h of saleable product, with a maximum feed top size near 550 mm and target fractions of 0–5, 5–20, 20–40 mm and ground filler.
| Parameter | Indicative value / method |
|---|---|
| Raw material | Limestone · 30–150 MPa · abrasion low |
| Design throughput | 110 t/h saleable product (100–250 t/h scenario band) |
| Maximum feed size | ~550 mm |
| Target product | 0–5, 5–20, 20–40 mm and ground filler |
| Loose bulk density | 1.35 t/m³ |
| Suggested circuit | jaw or impact → screen → optional grinding mill |

Why noise and vibration appears in this circuit
Noise limits at the site boundary are exceeded. In a limestone high-altitude site this is usually a system symptom rather than a single machine fault. The cheapest fix is usually a settings change; the most expensive is a new machine.
- the crusher and screen are mounted without adequate isolation
- the plant is arranged with its loudest face toward the boundary
- worn bearings and loose liners add impact noise
Record the setting before adjusting it, or the baseline is lost. Before changing a crusher setting, check these in order: 1) measure boundary noise at the worst-case operating state; 2) log vibration on screen bearings; 3) inspect isolation mounts during planned stops. Agree the acceptance test and sampling method before the order is placed.
Recommended equipment configuration
For limestone at 110 t/h the working train is jaw or impact → screen → optional grinding mill. The equipment list is fixed only after feed gradation, moisture and saleable fractions are confirmed — the same nominal capacity can require different crushers for limestone and for a softer rock. The reference conditions should be attached to every figure quoted.
| Parameter | Indicative value / method |
|---|---|
| Feeding | Vibrating grizzly feeder, VFD control, ~138 t/h design margin |
| Primary reduction | Jaw / impact crusher, nominal CSS ~22 mm at the secondary stage |
| Secondary / tertiary | screen |
| Screening | Multi-deck screen sized for 30% circulating load |
| Conveying | Belts sized for fresh feed + return stream, 1.35 t/m³ bulk density |
| Control | Interlocked start-up, power-based feed trim, 300 kW order-of-magnitude connected load |
The corrective actions for noise and vibration are applied on top of this base circuit: isolate screen and crusher mounts and maintain them; orient the plant and use stockpiles as acoustic barriers; replace worn bearings and re-torque liner fasteners.

Operating settings and acceptance checks
Settings must be recorded at commissioning and re-checked after every liner change. For this circuit the starting point is a secondary CSS near 22 mm, a circulating load around 30% and a screen efficiency target above 90%. Record the setting before adjusting it, or the baseline is lost.
- Measure boundary noise at the worst-case operating state
- Log vibration on screen bearings
- Inspect isolation mounts during planned stops
| Parameter | Indicative value / method |
|---|---|
| Capacity | Measured over a full shift, saleable tonnes, 110 t/h nominal |
| Grading | Full sieve analysis, agreed standard, 0–5, 5–20, 20–40 mm and ground filler |
| Crusher setting | CSS measured and logged, ~22 mm starting point |
| Power | Main-drive current at steady feed, 300 kW connected load |
| Wear | Liner mass before and after, cost per saleable tonne |
Agree the acceptance test and sampling method before the order is placed. All figures published on this site are nominal engineering values; actual performance depends on feed gradation, moisture, crusher setting and screening efficiency.
Cost, risk and what to confirm in writing
Compare this plant as cost per saleable tonne, not purchase price. Energy, wear parts, labour and downtime dominate the operating cost for limestone, while drive and cooling margins determines how much lost production actually costs. The cheapest fix is usually a settings change; the most expensive is a new machine.
- Ask every supplier for the same flow sheet and mass balance, including the 30% return stream.
- State the Incoterm, named port, civils scope, erection scope and a two-year spares list in the quotation.
- Model annual output as 110 t/h × scheduled hours × realistic utilisation (often 75–90%), not as nameplate × 8,760 hours.
- Agree the sampling method, sieve standard and acceptance test before the order is placed.
The reference conditions should be attached to every figure quoted. Agree the acceptance test and sampling method before the order is placed. Send your material, feed size, target capacity and product sizes to HAMAC Machinery for a comparable configuration and budget.